Cartis diligence evidence schedule

EdgeCore Florence Tech Park

PRJ-1150 · Site · Florence, Arizona, United States

Record last updated Oct 28, 2026

Scope and capacity

EdgeCore’s Florence, Arizona concept is a ten-building campus on roughly 230 acres. Town planning materials show ten two-story, 72 MW buildings, four campus areas and three substation areas; the 720 MW total is a design test fit, not permitted or operating capacity.

Headline: 720 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · EdgeCore Florence Tech Park | Florence | Arizona | US

Actual · EdgeCore Florence Tech Park (Project)

Claim 71922 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EdgeCore Florence Tech Park public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4136 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/arizona/

Lifecycle status · Proposed

Actual · EdgeCore Florence Tech Park (Project)

Claim 71923 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EdgeCore Florence Tech Park public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4136 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/arizona/

Reported capacity · 720 MW

Planned / design or future potential · EdgeCore Florence Tech Park (Project)

Claim 71924 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. EdgeCore Florence Tech Park public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4136 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/arizona/

Capacity basis · 720 MW future full build site capacity; not measured operating IT load.

Actual · EdgeCore Florence Tech Park (Project)

Claim 71925 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EdgeCore Florence Tech Park public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4136 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/arizona/

Building count · 10 buildings

Actual · EdgeCore Florence Tech Park (Project)

Claim 77854 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. EdgeCore Florence ten-building test fit

    Town of Florence · Document date: Sep 18, 2025 · Primary

    Source reference: SRC-4445 · Government record · Recorded authority: Official primary

    Source URL

    https://www.florenceaz.gov/wp-content/uploads/2025/08/September-18-2025-Agenda-Packet-PZ.pdf

Gross floor area · 7,840,000 square feet

Reported rounded · EdgeCore Florence Tech Park (Project)

Claim 77857 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Dobson Farms EdgeCore traffic analysis

    Town of Florence · Document date: Oct 7, 2025 · Primary

    Source reference: SRC-4446 · Government record · Recorded authority: Official primary

    Source URL

    https://www.florenceaz.gov/wp-content/uploads/2025/08/October-7-2025-Agenda-Packet.pdf

Counterparties and capital

EdgeCore · Developer · CMP-1531

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.