Scope and capacity
EdgeCore Culpeper Campus is a physical data-center campus. EdgeCore Culpeper Campus is located in Nalles Mill Road / Culpeper Technology Zone, VA, US and is a data center campus in preconstruction status.
Headline: 196 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (20)
Current campus area · 93 acres
Reported rounded · EdgeCore Culpeper Campus (Project)
Claim 40941 · Recorded claim type: Reported rounded · Review: Approved with conflict · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Current floor area · 920,000 square feet
Reported rounded · EdgeCore Culpeper Campus (Project)
Claim 40943 · Recorded claim type: Reported rounded · Review: Approved with conflict · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Current building count · 2 data centers
Reported rounded · EdgeCore Culpeper Campus (Project)
Claim 40945 · Recorded claim type: Reported rounded · Review: Approved with conflict · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Current initial IT capacity · 196 MW critical IT
Planned / design or future potential · EdgeCore Culpeper Campus (Project)
Claim 40947 · Recorded claim type: Reported rounded · Review: Approved with conflict · Claim date: Not stated
Headline treatment: Selected headline
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Current capacity availability target · 2029-H1
Forecast · EdgeCore Culpeper Campus (Project)
Claim 40949 · Recorded claim type: Forecast · Review: Approved with conflict · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Canonical operator · EdgeCore Digital Infrastructure
Actual · EdgeCore Culpeper Campus (Project)
Claim 40950 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore announces new hyperscale data center market in Culpeper
EdgeCore · Document date: Jul 18, 2024 · Corroborating
Source reference: SRC-2305 · Company announcement · Recorded authority: Party primary
Source URL
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Roadmap operator edgeconnex correct · False
Actual · EdgeCore Culpeper Campus (Project)
Claim 40951 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore announces new hyperscale data center market in Culpeper
EdgeCore · Document date: Jul 18, 2024 · Corroborating
Source reference: SRC-2305 · Company announcement · Recorded authority: Party primary
Source URL
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Predecessor developer · Cielo Digital Infrastructure
Actual · EdgeCore Culpeper Campus (Project)
Claim 40952 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore plans 216 MW Culpeper campus
Data Center Dynamics · Document date: Jul 18, 2024 · Corroborating
Source reference: SRC-2308 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/edgecore-plans-216mw-data-center-campus-in-virginias-culpeper-county/
https://www.datacenterdynamics.com/en/news/edgecore-plans-216mw-data-center-campus-in-virginias-culpeper-county/
- Virginia's Culpeper County approves Cielo data center proposal
Data Center Dynamics · Document date: Dec 13, 2023 · Primary
Source reference: SRC-2307 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/virginias-culpeper-county-approves-cielo-digital-infrastructure-data-center-proposal/
https://www.datacenterdynamics.com/en/news/virginias-culpeper-county-approves-cielo-digital-infrastructure-data-center-proposal/
Site acquired by edgecore · True
Actual · EdgeCore Culpeper Campus (Project)
Claim 40953 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore announces new hyperscale data center market in Culpeper
EdgeCore · Document date: Jul 18, 2024 · Primary
Source reference: SRC-2305 · Company announcement · Recorded authority: Party primary
Source URL
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
- EdgeCore plans 216 MW Culpeper campus
Data Center Dynamics · Document date: Jul 18, 2024 · Corroborating
Source reference: SRC-2308 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/edgecore-plans-216mw-data-center-campus-in-virginias-culpeper-county/
https://www.datacenterdynamics.com/en/news/edgecore-plans-216mw-data-center-campus-in-virginias-culpeper-county/
Campus location · Culpeper Technology Zone / Nalles Mill Road
Actual · EdgeCore Culpeper Campus (Project)
Claim 40954 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Virginia's Culpeper County approves Cielo data center proposal
Data Center Dynamics · Document date: Dec 13, 2023 · Corroborating
Source reference: SRC-2307 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/virginias-culpeper-county-approves-cielo-digital-infrastructure-data-center-proposal/
https://www.datacenterdynamics.com/en/news/virginias-culpeper-county-approves-cielo-digital-infrastructure-data-center-proposal/
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Current status · Preconstruction
Actual · EdgeCore Culpeper Campus (Project)
Claim 40955 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Future potential survives current plan verified · False
Actual · EdgeCore Culpeper Campus (Project)
Claim 40957 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore announces new hyperscale data center market in Culpeper
EdgeCore · Document date: Jul 18, 2024 · Corroborating
Source reference: SRC-2305 · Company announcement · Recorded authority: Party primary
Source URL
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Conservation area · 30 acres
Reported rounded · EdgeCore Culpeper Campus (Project)
Claim 40958 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Cooling system · Closed loop chilled water
Actual · EdgeCore Culpeper Campus (Project)
Claim 40959 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Target water usage effectiveness · 0.01 liters per kWh maximum
Planned / design or future potential · EdgeCore Culpeper Campus (Project)
Claim 40960 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Single tenant model · True
Actual · EdgeCore Culpeper Campus (Project)
Claim 40961 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Direct to chip liquid cooling supported · True
Actual · EdgeCore Culpeper Campus (Project)
Claim 40962 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Utility provider · Rappahannock Electric Cooperative
Actual · EdgeCore Culpeper Campus (Project)
Claim 40963 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore announces new hyperscale data center market in Culpeper
EdgeCore · Document date: Jul 18, 2024 · Primary
Source reference: SRC-2305 · Company announcement · Recorded authority: Party primary
Source URL
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Corroborating
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Utility service commitment documented · False
Actual · EdgeCore Culpeper Campus (Project)
Claim 40964 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore announces new hyperscale data center market in Culpeper
EdgeCore · Document date: Jul 18, 2024 · Corroborating
Source reference: SRC-2305 · Company announcement · Recorded authority: Party primary
Source URL
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
https://edgecore.com/resources/press-releases/edgecore-digital-infrastructure-announces-new-hyperscale-data-center-market-in-culpeper-virginia
- Culpeper Data Centers
EdgeCore · Document date: Not stated · Primary
Source reference: SRC-2304 · Recorded authority: Party primary
Source URL
https://edgecore.com/locations/culpeper-data-centers
https://edgecore.com/locations/culpeper-data-centers
Rezoning approval inherited · True
Actual · EdgeCore Culpeper Campus (Project)
Claim 40965 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- EdgeCore plans 216 MW Culpeper campus
Data Center Dynamics · Document date: Jul 18, 2024 · Corroborating
Source reference: SRC-2308 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/edgecore-plans-216mw-data-center-campus-in-virginias-culpeper-county/
https://www.datacenterdynamics.com/en/news/edgecore-plans-216mw-data-center-campus-in-virginias-culpeper-county/
- Virginia's Culpeper County approves Cielo data center proposal
Data Center Dynamics · Document date: Dec 13, 2023 · Primary
Source reference: SRC-2307 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/virginias-culpeper-county-approves-cielo-digital-infrastructure-data-center-proposal/
https://www.datacenterdynamics.com/en/news/virginias-culpeper-county-approves-cielo-digital-infrastructure-data-center-proposal/
Counterparties and capital
Cielo Digital Infrastructure · Developer · CMP-1065
EdgeCore Digital Infrastructure · Developer · CMP-1064
Rappahannock Electric Cooperative · Utility provider · CMP-1067
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.