Cartis diligence evidence schedule
EcoDataCenter Falun Campus
PRJ-0022 · Site · Falun / Ingarvet, W, Sweden
Captured 2026-09-06T04:12:49.325Z · Record last updated 2026-08-22
SHA-256: 1b5abe0f7a867c9a2d66f5a9ea1ce7f2da175883b9745f66bf7618fe7b255f33
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
EcoDataCenter's Falun main site is an operating Nordic data-center campus with heat recovery and renewable power access. Expansion announced in 2023 has produced two additional wooden data-center buildings, but the announced 45 MW site target is retained as a target until live capacity is explicitly confirmed.
Headline: 80 MW Utility capacity
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Operational Status · Operating
actual · EcoDataCenter Falun Campus (project)
Claim 3038 · Review: Approved · Claim date: Not published
- Why wood works for data centers
EcoDataCenter · Document date: 2025-10-01 · Corroborating
https://ecodatacenter.tech/press/why-wood-works-for-data-centers-3405816 - EcoDataCenter 1 – Main Site Falun
EcoDataCenter · Document date: Not published · Primary
https://ecodatacenter.tech/data-centers/eco-data-center-1
Site Address · Slaggvarpsvägen 21, 791 77 Falun
actual · EcoDataCenter Falun Campus (project)
Claim 3039 · Review: Approved · Claim date: Not published
- EcoDataCenter 1 – Main Site Falun
EcoDataCenter · Document date: Not published · Primary
https://ecodatacenter.tech/data-centers/eco-data-center-1
Opening Year · 2019
actual · Original Falun campus (phase)
Claim 3040 · Review: Approved · Claim date: Not published
- EcoDataCenter 1 – Main Site Falun
EcoDataCenter · Document date: Not published · Primary
https://ecodatacenter.tech/data-centers/eco-data-center-1
Operational Building Count · 4
actual · EcoDataCenter Falun Campus (project)
Claim 3041 · Review: Approved · Claim date: 2025-10-01T00:00:00+00:00
- Why wood works for data centers
EcoDataCenter · Document date: 2025-10-01 · Primary
https://ecodatacenter.tech/press/why-wood-works-for-data-centers-3405816
Built Building Count · 2
actual · 2023 Falun expansion (phase)
Claim 3042 · Review: Approved · Claim date: 2025-10-01T00:00:00+00:00
- Why wood works for data centers
EcoDataCenter · Document date: 2025-10-01 · Primary
https://ecodatacenter.tech/press/why-wood-works-for-data-centers-3405816
Utility Service Capacity · 80 MW
actual · EcoDataCenter Falun Campus (project)
Claim 3043 · Review: Approved · Claim date: 2022-02-23T00:00:00+00:00
Headline treatment: Selected headline
- EcoDataCenter in Falun secures a future power supply of 80 MW from renewable sources
EcoDataCenter · Document date: 2022-02-23 · Primary
https://ecodatacenter.tech/press/ecodatacenter-in-falun-secures-a-future-power-supply-of-80-mw-from-renewable-sources-3229138
Expansion Investment · €200,000,000
transaction scope · 2023 Falun expansion (phase)
Claim 3045 · Review: Approved · Claim date: 2023-11-27T00:00:00+00:00
- EcoDataCenter will more than double the capacity at EcoDataCenter 1 in Sweden
EcoDataCenter · Document date: 2023-11-27 · Primary
https://ecodatacenter.tech/press/ecodatacenter-will-more-than-double-the-capacity-at-ecodatacenter-1-in-sweden-3288868
Primary Structure · Engineered timber / wood
actual · 2023 Falun expansion (phase)
Claim 3048 · Review: Approved · Claim date: 2025-10-01T00:00:00+00:00
- Why wood works for data centers
EcoDataCenter · Document date: 2025-10-01 · Primary
https://ecodatacenter.tech/press/why-wood-works-for-data-centers-3405816
Heat Recovery · Surplus heat supports district/pellet production
actual · EcoDataCenter Falun Campus (project)
Claim 3049 · Review: Approved · Claim date: Not published
- NIB finances data centres in Sweden
Nordic Investment Bank · Document date: 2024-07-10 · Corroborating
https://www.nib.int/news/nib-finances-data-centres-in-sweden - EcoDataCenter in Falun secures a future power supply of 80 MW from renewable sources
EcoDataCenter · Document date: 2022-02-23 · Corroborating
https://ecodatacenter.tech/press/ecodatacenter-in-falun-secures-a-future-power-supply-of-80-mw-from-renewable-sources-3229138 - EcoDataCenter 1 – Main Site Falun
EcoDataCenter · Document date: Not published · Primary
https://ecodatacenter.tech/data-centers/eco-data-center-1
Customer Deployment · CoreWeave AI cloud with thousands of NVIDIA Blackwell GPUs
actual · CoreWeave AI deployment (phase)
Claim 3050 · Review: Approved · Claim date: 2024-08-28T00:00:00+00:00
- EcoDataCenter brings the world's most advanced AI technology to Sweden
EcoDataCenter · Document date: 2024-08-28 · Primary
https://ecodatacenter.tech/press/ecodatacenter-brings-the-worlds-most-advanced-ai-technology-to-sweden-3339095
Network Upgrade · Arelion PoP with 400G/800G coherent optics
actual · EcoDataCenter Falun Campus (project)
Claim 3051 · Review: Approved · Claim date: 2025-06-24T00:00:00+00:00
- Arelion connects EcoDataCenter to its Nordic AI superhighway
EcoDataCenter · Document date: 2025-06-24 · Primary
https://ecodatacenter.tech/press/arelion-connects-ecodatacenter-to-its-nordic-ai-superhighway-3393205
Counterparties and capital
Areim · Owner · CMP-0094
Areim DC Fund · Owner · CMP-0095
Arelion · Operator · CMP-0100
CoreWeave · Customer · CMP-0099
EcoDataCenter · Operator · CMP-0093
Ellevio · Utility Provider · CMP-0097
Falu Energi & Vatten · Supplier · CMP-0096
Falu kommun · Landowner · CMP-0098
€200,000,000 · 2023-11-27
EcoDataCenter 1 Falun expansion announcement.
EcoDataCenter (Sponsor) · EcoDataCenter (Sponsor And Borrower Context)
Financing record 21; claim-specific source links appear in the exhibit sources where published.
€450,000,000 · 2025-03-05
Areim DC Fund level; growth capital for EcoDataCenter, not Falun-only.
Areim (Adviser) · Areim DC Fund (Other) · Areim DC Fund (Capital Vehicle)
Financing record 23; claim-specific source links appear in the exhibit sources where published.
€600,000,000 · 2025-09-09
Primarily Falun and Borlänge; no site allocation, so amount is contextual for Falun.
Deutsche Bank Private Credit and Infrastructure (Lender) · EcoDataCenter (Borrower)
Financing record 22; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.