EcoDataCenter Falun Campus

Falun / Ingarvet, W, SwedenOperating
Evidence
Utility capacity
80 MW
Updated
Oct 28, 2026
Utility
Ellevio

EcoDataCenter's 2025 annual report states that buildings C and D at Falun were completed and commissioned, with reported site capacity of 41 MW at year-end 2025; the report does not establish that figure as IT load. Construction of buildings E and F began in 2025, with F forecast for Q3 2026 and E for the end of Q4 2026; the report's 65 MW figure is the expected total after both are completed, not confirmed current capacity. EcoDataCenter's Falun main site is an operating Nordic data center campus with heat recovery and renewable power access. The expansion announced in 2023 produced two additional wooden data center buildings and previously carried a 45 MW site target. The later annual-report figures should not be treated as proof that the E/F expansion has opened.

Capacity

Utility service capacity

Actual

80 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Original Falun campusOperational

4 buildings

Campus baseline only. The operator's four-building count is not converted to MW.

2023 Falun expansionPartially operational

2 buildings

The 2023 release forecast first delivery in Q3 2024 and full completion in Q2 2025. Current operator material verifies buildings, not the full 45 MW as live IT capacity.

CoreWeave AI deploymentUnder construction

Customer deployment is distinct from facility capacity and from the wider Falun expansion.

Milestones (6)
Falun first facility opened

2019 · Recorded actual event

Completed · Commercial operation

Source not linked
Future renewable power supply announced

Feb 23, 2022 · Recorded actual event

Completed · Announced

Source not linked
EUR 200m Falun expansion and 45 MW target announced

Nov 27, 2023 · Recorded actual event

Completed · Announced

Source not linked
CoreWeave AI deployment announced

Aug 28, 2024 · Recorded actual event

Completed · Customer commitment

Source not linked
Arelion PoP and coherent optics announced

Jun 24, 2025 · Recorded actual event

Completed · Announced

Source not linked
Operator reports two expansion buildings built

Oct 2025 · Recorded actual event

Completed · Construction completed

Source not linked

Participants

Arelion

Operator

Sources by role
CoreWeave

Customer

Sources by role
EcoDataCenter

Operator

Sources by role
Falu kommun

Landowner

Sources by role
Other participants (2)
Ellevio

Utility provider

Sources by role

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Expansion investment

Transaction scope

€200,000,000

2023 Falun expansion · Phase

Source

Financing records

Investment commitment

€200,000,000

Nov 27, 2023

EcoDataCenter 1 Falun expansion announcement.

Parties & sources

EcoDataCenter (Sponsor / Sponsor and borrower context)

Equity investment

€450,000,000

Mar 5, 2025

Areim DC Fund level; growth capital for EcoDataCenter, not Falun-only.

Parties & sources

Areim (Adviser) · Areim DC Fund (Other / Capital vehicle)

Debt financing

€600,000,000

Sep 9, 2025

Primarily Falun and Borlänge; no site allocation, so amount is contextual for Falun.

Parties & sources

Deutsche Bank Private Credit and Infrastructure (Lender) · EcoDataCenter (Borrower)

Site & development

Site address

Actual

Slaggvarpsvägen 21, 791 77 Falun

Source

Operational building count

Actual

4 buildings

Source

Built building count

Actual

2 buildings

2023 Falun expansion · Phase

Source

Technical specifications

Network upgrade

Actual

Arelion PoP with 400G/800G coherent optics

Source

Additional project facts

Operational status

Actual

Operating

Source

Opening year

Actual

2019

Original Falun campus · Phase

Source

Primary structure

Actual

Engineered timber / wood

2023 Falun expansion · Phase

Source

Heat recovery

Actual

Surplus heat supports district/pellet production

Source

Customer deployment

Actual

CoreWeave AI cloud with thousands of NVIDIA Blackwell GPUs

CoreWeave AI deployment · Phase

Source

Infrastructure & permits

Technical details (3)
Utility service

Secured or contracted

80 MW

Renewable power supply with Falu Energi & Vatten and Ellevio grid reinforcement; not live IT capacity.

Heat reuse

Reported context

Surplus heat supports district/pellet-production systems; no delivered heat figure captured.

Fiber

Planned or represented

Existing Arelion PoP; 400 G/800 G coherent-optics upgrade announced with delivery from early Q3 2025. Exact completion unverified; optics capability is not a site-level bandwidth commitment.

Public-source research. Plans may change. See Evidence for sources and qualifications.