Cartis diligence evidence schedule
DayOne Lahti Data Center Campus
PRJ-0018 · Site · Lahti / Kiveriö, Finland
Captured 2026-09-06T04:13:02.721Z · Record last updated 2026-08-22
SHA-256: 5d566b08fe3a001a390035faf626c30c78046d05c23e27284aadd0c828bad700
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
DayOne began construction of its Kiveriö campus in April 2026. The first building is planned for 50 MW of IT load within a 128 MW potential campus, with TikTok confirmed as principal tenant.
Headline: —
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Current Status · Under construction
actual · DayOne Lahti Data Center Campus (project)
Claim 2240 · Review: Approved · Claim date: Not published
- TikTok investoi miljardin Lahden datakeskukseen
City of Lahti · Document date: 2026-04-10 · Corroborating
https://www.lahti.fi/uutiset/tiktok-investoi-miljardin-lahden-datakeskukseen/ - DayOne data center construction to start in Lahti — SRV strengthens its position
SRV Group · Document date: 2026-04-07 · Primary
https://news.cision.com/srv-yhtiot-oyj/r/dayone-data-center-construction-to-start-in-lahti---srv-strengthens-its-position-in-the-growing-mark%2Cc4331404
Site Area · 98,901 square metres
actual · DayOne Lahti Data Center Campus (project)
Claim 2241 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Site Location · Kiveriö; Ilmarisentie 3 / Väinämöisentie 2a
actual · DayOne Lahti Data Center Campus (project)
Claim 2242 · Review: Approved · Claim date: Not published
- DayOne data center construction to start in Lahti — SRV strengthens its position
SRV Group · Document date: 2026-04-07 · Corroborating
https://news.cision.com/srv-yhtiot-oyj/r/dayone-data-center-construction-to-start-in-lahti---srv-strengthens-its-position-in-the-growing-mark%2Cc4331404 - Datakeskuksen rakentamislupa rakennus- ja ympäristölupalautakuntaan
City of Lahti · Document date: 2025-10-02 · Corroborating
https://www.lahti.fi/uutiset/datakeskuksen-rakentamislupa-rakennus-ja-ymparistolupalautakuntaan/ - A €1.2 billion data centre to be built in Kiveriö, Lahti
City of Lahti · Document date: 2025-08-14 · Primary
https://www.lahti.fi/en/news/a-e1-2-billion-data-centre-to-be-built-in-kiverio-lahti/
Planned It Capacity · 50 MW IT
Planned / design or future potential · Lahti first 50 MW building (phase)
Claim 2243 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
Headline treatment: Phase scope; not a whole-site figure
- TikTok announces additional €1 Billion investment in Finland
TikTok · Document date: 2026-04-07 · Corroborating
https://newsroom.tiktok.com/tiktok-announces-additional-1-billion-investment-in-finland?lang=en-150 - DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Potential It Capacity · 128 MW IT
Planned / design or future potential · Lahti full campus potential (phase)
Claim 2244 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
Headline treatment: Phase scope; not a whole-site figure
- TikTok announces additional €1 Billion investment in Finland
TikTok · Document date: 2026-04-07 · Corroborating
https://newsroom.tiktok.com/tiktok-announces-additional-1-billion-investment-in-finland?lang=en-150 - DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Permit Application Floor Area · 40,000 square metres
reported rounded · Lahti permit and site preparation (phase)
Claim 2245 · Review: Approved · Claim date: 2025-10-02T00:00:00+00:00
- Datakeskuksen rakentamislupa rakennus- ja ympäristölupalautakuntaan
City of Lahti · Document date: 2025-10-02 · Primary
https://www.lahti.fi/uutiset/datakeskuksen-rakentamislupa-rakennus-ja-ymparistolupalautakuntaan/
Data Hall Storeys · 2 storeys
proposal · Lahti permit and site preparation (phase)
Claim 2246 · Review: Approved · Claim date: 2025-10-02T00:00:00+00:00
- Datakeskuksen rakentamislupa rakennus- ja ympäristölupalautakuntaan
City of Lahti · Document date: 2025-10-02 · Primary
https://www.lahti.fi/uutiset/datakeskuksen-rakentamislupa-rakennus-ja-ymparistolupalautakuntaan/
Construction Start · Launched immediately after 2026-04-07 contractor announcement
actual · Lahti first 50 MW building (phase)
Claim 2247 · Review: Approved · Claim date: 2026-04-07T00:00:00+00:00
- DayOne data center construction to start in Lahti — SRV strengthens its position
SRV Group · Document date: 2026-04-07 · Primary
https://news.cision.com/srv-yhtiot-oyj/r/dayone-data-center-construction-to-start-in-lahti---srv-strengthens-its-position-in-the-growing-mark%2Cc4331404
Ready For Service Target · 2027
Planned / design or future potential · Lahti first 50 MW building (phase)
Claim 2248 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne data center construction to start in Lahti — SRV strengthens its position
SRV Group · Document date: 2026-04-07 · Corroborating
https://news.cision.com/srv-yhtiot-oyj/r/dayone-data-center-construction-to-start-in-lahti---srv-strengthens-its-position-in-the-growing-mark%2Cc4331404 - DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Dayone Announced Investment · €1,200,000,000
forecast · DayOne Lahti Data Center Campus (project)
Claim 2249 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland - A €1.2 billion data centre to be built in Kiveriö, Lahti
City of Lahti · Document date: 2025-08-14 · Corroborating
https://www.lahti.fi/en/news/a-e1-2-billion-data-centre-to-be-built-in-kiverio-lahti/
Principal Tenant · TikTok
actual · DayOne Lahti Data Center Campus (project)
Claim 2251 · Review: Approved · Claim date: 2026-04-07T00:00:00+00:00 · Supersedes 2250
- TikTok investoi miljardin Lahden datakeskukseen
City of Lahti · Document date: 2026-04-10 · Corroborating
https://www.lahti.fi/uutiset/tiktok-investoi-miljardin-lahden-datakeskukseen/ - TikTok announces additional €1 Billion investment in Finland
TikTok · Document date: 2026-04-07 · Primary
https://newsroom.tiktok.com/tiktok-announces-additional-1-billion-investment-in-finland?lang=en-150
Tiktok Announced Investment · €1,000,000,000
transaction scope · DayOne Lahti Data Center Campus (project)
Claim 2252 · Review: Approved · Claim date: 2026-04-07T00:00:00+00:00
- TikTok investoi miljardin Lahden datakeskukseen
City of Lahti · Document date: 2026-04-10 · Corroborating
https://www.lahti.fi/uutiset/tiktok-investoi-miljardin-lahden-datakeskukseen/ - TikTok announces additional €1 Billion investment in Finland
TikTok · Document date: 2026-04-07 · Primary
https://newsroom.tiktok.com/tiktok-announces-additional-1-billion-investment-in-finland?lang=en-150
Power Connection Agreement · Executed with Lahti Energy
actual · DayOne Lahti Data Center Campus (project)
Claim 2253 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Grid Connection Contract Value · €38,000,000
transaction scope · DayOne Lahti Data Center Campus (project)
Claim 2254 · Review: Approved · Claim date: 2025-09-12T00:00:00+00:00
- Eltel to build grid connections for DayOne's Data Center — contract value EUR 38 million
Eltel Group · Document date: 2025-09-12 · Primary
https://www.eltelgroup.com/en/eltel-to-build-grid-connections-for-dayones-data-center-contract-value-eur-38-million/
Grid Connection Completion Target · 2027 Q1
Planned / design or future potential · DayOne Lahti Data Center Campus (project)
Claim 2255 · Review: Approved · Claim date: 2025-09-12T00:00:00+00:00
- Eltel to build grid connections for DayOne's Data Center — contract value EUR 38 million
Eltel Group · Document date: 2025-09-12 · Primary
https://www.eltelgroup.com/en/eltel-to-build-grid-connections-for-dayones-data-center-contract-value-eur-38-million/
Cooling Design · Air cooled chiller; no freshwater cooling
design · DayOne Lahti Data Center Campus (project)
Claim 2256 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Waste Heat Reuse · Under exploration with local partners
design · DayOne Lahti Data Center Campus (project)
Claim 2257 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland - A €1.2 billion data centre to be built in Kiveriö, Lahti
City of Lahti · Document date: 2025-08-14 · Corroborating
https://www.lahti.fi/en/news/a-e1-2-billion-data-centre-to-be-built-in-kiverio-lahti/
Projected Operational Jobs · 100 jobs
forecast · DayOne Lahti Data Center Campus (project)
Claim 2258 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Peak Construction Workers · 1,000 workers
forecast · DayOne Lahti Data Center Campus (project)
Claim 2259 · Review: Approved · Claim date: 2025-08-14T00:00:00+00:00
- DayOne announces flagship hyperscale data center project in Lahti, Finland
DayOne Data Centers · Document date: 2025-08-14 · Primary
https://dayonedc.com/markets/dayone-announces-flagship-hyperscale-data-center-project-in-lahti-finland
Counterparties and capital
City of Lahti · Government Authority · CMP-0073
DayOne Data Centers · Operator · CMP-0071
Eltel Networks · Contractor · CMP-0077
Kiinteistö Oy Lahden Ilmarisentie 3 · Owner · CMP-0075
Lahti Energy · Utility Provider · CMP-0074
SRV Group Plc · Contractor · CMP-0076
TikTok · Tenant · CMP-0072
€1,200,000,000 · 2025-08-14
DayOne aggregate project estimate; no financing sources or spend schedule disclosed.
DayOne Data Centers (Sponsor)
Financing record 16; claim-specific source links appear in the exhibit sources where published.
€1,000,000,000 · 2026-04-07
TikTok investment/customer scope; not additive to DayOne's project estimate and not site financing.
TikTok (Sponsor)
Financing record 17; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.