DayOne Lahti Data Center Campus
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
- Utility
- Lahti Energy
DayOne began construction of its Kiveriö campus in April 2026. The first building is planned for 50 MW of IT load within a 128 MW potential campus, with TikTok confirmed as principal tenant.
Capacity
Planned IT capacity
Planned / design or future potential50 MW
Lahti first 50 MW building · Phase
Phase scope; not a whole-site figure
SourcePotential IT capacity
Planned / design or future potential128 MW
Lahti full campus potential · Phase
Phase scope; not a whole-site figure
SourceOperating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Application covered a two-story data hall and ancillary buildings; construction later began.
1 building
50 MW IT design within the larger 128 MW potential site.
Future envelope only; no completed or contracted full-site capacity inferred.
Milestones (5)
Aug 14, 2025 · Recorded actual event
Completed · Announced
Source not linkedOct 2, 2025 · Recorded actual event
Completed · Permit filed
Source not linkedApr 7, 2026 · Recorded actual event
Completed · Construction started
Source not linkedApr 7, 2026 · Recorded actual event
Completed · Customer commitment
Source not linked2027 · Forecast / planned record
Forecast · Ready for service
Source not linkedParticipants
Operator
Sources by role
Operator (1)
- TikTok investoi miljardin Lahden datakeskukseen · Apr 10, 2026 · Corroborating
Operator (1)
- DayOne announces flagship hyperscale data center project in Lahti, Finland · Aug 14, 2025 · Primary
Owner
Sources by role
Owner (1)
- Datakeskuksen rakentamislupa rakennus- ja ympäristölupalautakuntaan · Oct 2, 2025 · Primary
Tenant
Sources by role
Tenant (1)
- TikTok investoi miljardin Lahden datakeskukseen · Apr 10, 2026 · Corroborating
Tenant (1)
- TikTok announces additional €1 Billion investment in Finland · Apr 7, 2026 · Primary
Other participants (4)
Government authority
Sources by role
Government authority (1)
- TikTok investoi miljardin Lahden datakeskukseen · Apr 10, 2026 · Corroborating
Government authority (1)
- Datakeskuksen rakentamislupa rakennus- ja ympäristölupalautakuntaan · Oct 2, 2025 · Corroborating
Government authority (1)
- A €1.2 billion data centre to be built in Kiveriö, Lahti · Aug 14, 2025 · Primary
Contractor
Sources by role
Contractor (1)
- Eltel to build grid connections for DayOne's Data Center — contract value EUR 38 million · Sep 12, 2025 · Primary
Utility provider
Sources by role
Utility provider (1)
- DayOne announces flagship hyperscale data center project in Lahti, Finland · Aug 14, 2025 · Primary
Contractor
Sources by role
Contractor (1)
- TikTok investoi miljardin Lahden datakeskukseen · Apr 10, 2026 · Corroborating
Contractor (1)
- DayOne data center construction to start in Lahti — SRV strengthens its position · Apr 7, 2026 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
€1,200,000,000Aug 14, 2025
DayOne aggregate project estimate; no financing sources or spend schedule disclosed.
Parties & sources
DayOne Data Centers (Sponsor)
Sources (2)
Investment commitment
€1,000,000,000Apr 7, 2026
TikTok investment/customer scope; not additive to DayOne's project estimate and not site financing.
Parties & sources
TikTok (Sponsor)
Sources (2)
- TikTok investoi miljardin Lahden datakeskukseen · Apr 10, 2026
- TikTok announces additional €1 Billion investment in Finland · Apr 7, 2026
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (6)
Under construction
50 MW IT
First-building planned IT load; no operating capacity.
Planned or represented
128 MW IT
Full campus potential only.
Under construction
Power connection agreement and Eltel delivery contract; rating undisclosed.
Secured or contracted
€38,000,000 contract value
Contract value is not capacity, capex total or financing.
Planned or represented
Design claim not operating performance.
Potential or planned
Integration under exploration; no executed heat-offtake terms captured.
Project map
Building · Under review
Lahti first data center building and ancillary works
City of Lahti
Oct 2, 2025
Sources (1)
- Datakeskuksen rakentamislupa rakennus- ja ympäristölupalautakuntaan · Oct 2, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.