Data center siteSite record

DayOne Lahti Data Center Campus

Lahti / Kiveriö, FinlandUnder construction
Capacity
No public figure
Lead participant
DayOne Data Centers
Operator
Last updated
Aug 22, 2026
Most recent public record update

About DayOne Lahti Data Center Campus

DayOne began construction of its Kiveriö campus in April 2026. The first building is planned for 50 MW of IT load within a 128 MW potential campus, with TikTok confirmed as principal tenant.

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design50 MWDesign · Lahti first 50 MW building
Future Potential128 MWForecast · Lahti full campus potential

Development

3 phases · 5 milestones
Lahti permit and site preparationAnnounced Or Preconstruction

Application covered a two-story data hall and ancillary buildings; construction later began.

1 building

Lahti first 50 MW buildingUnder Construction

50 MW IT design within the larger 128 MW potential site.

1 building

Lahti full campus potentialPlanned

Future envelope only; no completed or contracted full-site capacity inferred.

Aug 14, 2025
DayOne announces €1.2B Lahti campus
Completed
Oct 2, 2025
Lahti publishes building-permit application scope
Completed
Apr 7, 2026
SRV launches Lahti construction
Completed
Apr 7, 2026
TikTok confirms Lahti investment
Completed
Jan 1, 2027
First Lahti building targeted for operation
Forecast

Infrastructure

Electric GridUnder Construction

50 MW IT

First-building planned IT load; no operating capacity.

Electric GridPlanned Or Represented

128 MW IT

Full campus potential only.

Electric GridUnder Construction

Power connection agreement and Eltel delivery contract; rating undisclosed.

Electric GridSecured Or Contracted

€38,000,000 contract value

Contract value is not capacity, capex total or financing.

Cooling SystemPlanned Or Represented

Design claim not operating performance.

Heat ReusePotential Or Planned

Integration under exploration; no executed heat-offtake terms captured.

Project map

0 of 1 project point mapped
Infrastructure facts
6
Mapped records
1
Capacity figures
3

No map point available

Power & interconnection: 4Cooling & water: 2

Facts & sources

Published claims and their source links.

19 facts
Current Status
Under construction
Actual
Site Area
98,901 square metres
Actual
Site Location
Kiveriö; Ilmarisentie 3 / Väinämöisentie 2a
Actual
Planned It Capacity
50 MW IT
Design
Potential It Capacity
128 MW IT
Forecast
Permit Application Floor Area
40,000 square metres
Reported Rounded
Data Hall Storeys
2 storeys
Proposal
Construction Start
Launched immediately after 2026-04-07 contractor announcement
Actual
Ready For Service Target
2027
Forecast
Dayone Announced Investment
€1,200,000,000
Forecast
Principal Tenant
TikTok
Actual
Tiktok Announced Investment
€1,000,000,000
Transaction Scope
Power Connection Agreement
Executed with Lahti Energy
Actual
Grid Connection Contract Value
€38,000,000
Transaction Scope
Grid Connection Completion Target
2027 Q1
Forecast
Cooling Design
Air cooled chiller; no freshwater cooling
Design
Waste Heat Reuse
Under exploration with local partners
Design
Projected Operational Jobs
100 jobs
Forecast
Peak Construction Workers
1,000 workers
Forecast