Skip to content
All records
Data center program / initiativeProgram record

DayOne Chonburi Tech Park Program

Amata City Chonburi, Chonburi, ThailandStatus Under Review
Capacity
See sites
2 constituent sites
Lead participant
DayOne Data Centers
Developer · Operator
Last updated
Aug 25, 2026
Most recent public record update

About DayOne Chonburi Tech Park Program

DayOne is building a two-site Chonburi platform anchored by CTP1 and prospective CTP2, with a long-run 1 GW power ambition. DayOne Chonburi Tech Park Program is located in Amata City Chonburi, Chonburi, TH and is a program in construction status. Participants include DayOne Data Centers as developer, DayOne Data Centers as operator, Digitalland Services (Thailand) Co., Ltd. as owner, Amata B.Grimm Renewable Energy as utility. Published specifications include 1 GW of future potential, 300 MW of operating IT capacity. Key milestones include DayOne and AMBRE sign renewable-power agreement (2025-11-10) and 42.5 MWp floating-solar supply targeted (2027). renewable power purchase — 42.5 MWp: Floating-solar supply targeted for 2027 and expected to integrate through PEA; allocation by site is not disclosed. grid integration: Tripartite integration described for the renewable supply; final service arrangements are not public.

Constituent sites

2 linked

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load300 MWActual · DayOne Chonburi Tech Park Program

Development

0 phases · 4 milestones
Nov 1, 2024
Thailand BOI approves Digitalland Services project
Completed
Nov 10, 2025
DayOne and Amata announce two-site growth plan
Completed
Nov 10, 2025
DayOne and AMBRE sign renewable-power agreement
Completed
Jan 1, 2027
42.5 MWp floating-solar supply targeted
Year

Infrastructure

Renewable Energy SupplySecured Or Contracted

42.5 MWp

Floating-solar supply targeted for 2027 and expected to integrate through PEA; allocation by site is not disclosed.

Electric GridPlanned Or Represented

Tripartite integration described for the renewable supply; final service arrangements are not public.

Constituent-site map

0 of 2 constituent sites mapped
Child-site facts
0
Mapped child sites
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

6 facts
Named Site Count
2 sites
Actual
Future Platform Power Envelope
1 GW
Actual
Ctp1 Is Construction Anchor
True
Actual
Ctp2 Governed By Mou
True
Actual
Thailand Program Investment Commitment
$1 billion
Actual
Current Ctp1 Power Capacity
300 MW
Actual