Data center siteSite record

DayOne Chonburi Tech Park 1

Amata City Chonburi Industrial Estate, Chonburi, ThailandUnder construction
Capacity
300 MW
Planned critical IT
Lead participant
DayOne Data Centers
Developer · Operator
Last updated
Aug 25, 2026
Most recent public record update

About DayOne Chonburi Tech Park 1

CTP1 is under construction at Amata City Chonburi and now carries a 300 MW power envelope after expansion from the original 180 MW plan. DayOne Chonburi Tech Park 1 is located in Amata City Chonburi Industrial Estate, Chonburi, TH and is a data center campus in construction status. Participants include DayOne Data Centers as developer, DayOne Data Centers as operator, Digitalland Services (Thailand) Co., Ltd. as owner, Amata Corporation as landowner. Published specifications include 300 MW of operating IT capacity. Development comprises CTP1 original two-phase build (construction), CTP1 expanded buildout (construction). Key milestones include Current DayOne page retains 2026 RFS target (2026) and UOB-led syndicate finances initial CTP1 phase (2026-03-06). grid capacity — 300 MW: Current CTP1 power envelope after expansion; not IT load and not operating capacity. Permitting includes investment promotion approval for Chonburi Tech Park 1 (approved). Capital records include green term loan of 28 THB billion for Initial-phase land acquisition, development, construction and eligible sustainability costs. UOB and transaction counsel report THB28 billion; one OCBC public post reported THB27 billion. Incentives include investment promotion approval (approved) for BOI approved the Digitalland Services Thailand hyperscale data center investment at THB28 billion. Tax/non-tax benefit amounts and conditions are not disclosed in the announcement.

Program relationships

1 linked

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load300 MWActual · DayOne Chonburi Tech Park 1
Onsite Generation42.5 MWActual · DayOne Chonburi Tech Park 1

Development

2 phases · 3 milestones
CTP1 original two-phase buildUnder Construction

March 2025 scope before adjacent-land expansion.

CTP1 expanded buildoutUnder Construction

Current power envelope; phase-level MW allocation and operating tranche remain undisclosed.

Mar 17, 2025
DayOne breaks ground at CTP1
Completed
Jan 1, 2026
Current DayOne page retains 2026 RFS target
Year
Mar 6, 2026
UOB-led syndicate finances initial CTP1 phase
Completed

Infrastructure

Electric GridUnder Construction

300 MW

Current CTP1 power envelope after expansion; not IT load and not operating capacity.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

16 facts
Current Power Capacity
300 MW
Actual
Green Term Loan Amount
28 THB billion
Actual
Groundbreaking Date
2025-03-17
Actual
Construction Status
True
Actual
Ready For Service Target Year
2026
Actual
Announced Development Phase Count
2 phases
Actual
Campus Area
122,000 square meters
Actual
Liquid Cooling Planned
True
Actual
Adjacent Expansion Land
16.3 acres
Actual
Boi Approved Investment
28 THB billion
Actual
Green Loan Funds Initial Phase
True
Actual
Green Loan Bank Count
6 banks
Actual
Leed Gold Or Higher Target
True
Actual
Floating Solar Supply Capacity
42.5 MWp
Actual
Renewable Supply Start Target Year
2027
Actual
Pea Grid Integration Planned
True
Actual