Cartis diligence evidence schedule
DATA4 Warsaw Jawczyce Campus
PRJ-0570 · Site · Jawczyce, Warsaw metropolitan area, Poland
Captured 2026-09-06T04:13:02.425Z · Record last updated 2026-08-26
SHA-256: 5cd2190b46f0396d87d7d2c15da61ca5493ee10a588d23793d4d003b9fd916f3
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
DATA4 opened its first Jawczyce facility in 2023 and inaugurated a second 10 MW facility in April 2026. The four-building campus can ultimately reach 60 MW.
Headline: 60 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Operating Status · Operational and expanding
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50809 · Review: Approved · Claim date: Not published
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Corroborating
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/ - Data Center Warsaw, Poland
DATA4 · Document date: Not published · Primary
https://www.data4group.com/en/data-centers-warsaw-poland/
First Facility Opening · 2023-05-23
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50810 · Review: Approved · Claim date: 2023-05-23T00:00:00+00:00
- The grand opening of the first DATA4 campus in Poland
DATA4 · Document date: 2023-05-23 · Primary
https://www.data4group.com/en/news-data4/data4-revolutionizing-connectivity-the-grand-opening-of-the-first-campus-in-poland/
Second Facility Opening · 2026-04-09
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50811 · Review: Approved · Claim date: 2026-04-09T00:00:00+00:00
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Primary
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/ - Inauguration of the DATA4 data center in Jawczyce
HOCHTIEF Polska · Document date: 2026-04-09 · Corroborating
https://www.hochtief.pl/en/bez-kategorii-pl-en/inauguration-of-the-data4-data-center-in-jawczyce/
Second Facility Capacity · 10 MW
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50812 · Review: Approved · Claim date: 2026-04-09T00:00:00+00:00
Headline treatment: Separate claim, not added to the headline
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Primary
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/
Site Area · 4 hectares
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50813 · Review: Approved · Claim date: Not published
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Corroborating
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/ - The grand opening of the first DATA4 campus in Poland
DATA4 · Document date: 2023-05-23 · Corroborating
https://www.data4group.com/en/news-data4/data4-revolutionizing-connectivity-the-grand-opening-of-the-first-campus-in-poland/ - Data Center Warsaw, Poland
DATA4 · Document date: Not published · Primary
https://www.data4group.com/en/data-centers-warsaw-poland/
Planned Facility Count · 4 facilities
Planned / design or future potential · DATA4 Warsaw Jawczyce Campus (project)
Claim 50814 · Review: Approved · Claim date: 2023-05-23T00:00:00+00:00
- The grand opening of the first DATA4 campus in Poland
DATA4 · Document date: 2023-05-23 · Primary
https://www.data4group.com/en/news-data4/data4-revolutionizing-connectivity-the-grand-opening-of-the-first-campus-in-poland/
Campus It Power Envelope · 60 MW
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50815 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Corroborating
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/ - The grand opening of the first DATA4 campus in Poland
DATA4 · Document date: 2023-05-23 · Corroborating
https://www.data4group.com/en/news-data4/data4-revolutionizing-connectivity-the-grand-opening-of-the-first-campus-in-poland/ - Data Center Warsaw, Poland
DATA4 · Document date: Not published · Primary
https://www.data4group.com/en/data-centers-warsaw-poland/
Planned Gross Floor Area · 50,000 square metres
Planned / design or future potential · DATA4 Warsaw Jawczyce Campus (project)
Claim 50816 · Review: Approved · Claim date: 2023-05-23T00:00:00+00:00
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Corroborating
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/ - The grand opening of the first DATA4 campus in Poland
DATA4 · Document date: 2023-05-23 · Primary
https://www.data4group.com/en/news-data4/data4-revolutionizing-connectivity-the-grand-opening-of-the-first-campus-in-poland/
Planned It Space · 15,000 square metres
Planned / design or future potential · DATA4 Warsaw Jawczyce Campus (project)
Claim 50817 · Review: Approved · Claim date: 2023-05-23T00:00:00+00:00
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Corroborating
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/ - The grand opening of the first DATA4 campus in Poland
DATA4 · Document date: 2023-05-23 · Primary
https://www.data4group.com/en/news-data4/data4-revolutionizing-connectivity-the-grand-opening-of-the-first-campus-in-poland/
First Facility Pue · 1.27
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50818 · Review: Approved · Claim date: Not published
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Primary
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/
Second Facility Certification · BREEAM Excellent
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50819 · Review: Approved · Claim date: Not published
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Primary
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/
Low Carbon Energy Share · 100 percent
actual · DATA4 Warsaw Jawczyce Campus (project)
Claim 50821 · Review: Approved · Claim date: Not published
- DATA4 expands in Poland with second data center near Warsaw
DATA4 · Document date: 2026-04-09 · Primary
https://www.data4group.com/en/news-data4/data4-expands-in-poland-with-second-data-center-near-warsaw/
Counterparties and capital
DATA4 Group · Developer · CMP-0078
Amount not disclosed · 2026-04-09
Nearly €200M invested in Poland; geographic scope is broader than a verified campus-only allocation and is not a financing close. Source wording: nearly EUR 200 million.
DATA4 Group (Sponsor)
Financing record 154; claim-specific source links appear in the exhibit sources where published.
Amount not disclosed · 2026-04-09
DATA4 plans around €600M in Poland by 2030; not current spend or Jawczyce-only financing. Source wording: approximately EUR 600 million by 2030.
DATA4 Group (Sponsor)
Financing record 155; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.