DATA4 Warsaw Jawczyce Campus

Jawczyce, Warsaw metropolitan area, PolandPartially operational
Evidence
Planned critical IT
60 MW
Updated
Oct 28, 2026

DATA4 opened its first Jawczyce facility in 2023 and inaugurated a second 10 MW facility in April 2026. The four-building campus can ultimately reach 60 MW.

Capacity

Second facility capacity

Actual

10 MW

Source

Campus IT power envelope

Actual

60 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

First facilityOperational

1 building

First of four planned campus facilities.

Second facilityOperational

1 building

BREEAM Excellent reported by DATA4.

Four-facility campus buildoutOperational

4 buildings

50,000 gross square metres and 15,000 square metres of IT space at full-campus scope.

Milestones (2)
DATA4 inaugurates first Poland facility

May 23, 2023 · Recorded actual event

Completed · Commercial operation

Source not linked
DATA4 inaugurates second Jawczyce facility

Apr 9, 2026 · Recorded actual event

Completed · Commercial operation

Source not linked

Participants

DATA4 Group

Developer

Sources by role
Developer (1)
Developer (1)
Developer (1)

Capital & incentives

Financing records

Investment commitment

Amount not disclosed

Apr 9, 2026

Nearly €200M invested in Poland; geographic scope is broader than a verified campus-only allocation and is not a financing close. Source wording: nearly EUR 200 million.

Parties & sources

DATA4 Group (Sponsor)

Investment commitment

Amount not disclosed

Apr 9, 2026

DATA4 plans around €600M in Poland by 2030; not current spend or Jawczyce-only financing. Source wording: approximately EUR 600 million by 2030.

Parties & sources

DATA4 Group (Sponsor)

Site & development

Site area

Actual

4 hectares

Source

Planned gross floor area

Actual

50,000 square metres

Source

Technical specifications

Low carbon energy share

Actual

100 percent

Source

Additional project facts

Operating status

Actual

Operational and expanding

Source

First facility opening

Actual

2023-05-23

Source

Second facility opening

Actual

2026-04-09

Source

Planned facility count

Actual

4 facilities

Source

Planned IT space

Actual

15,000 square metres

Source

First facility PUE

Actual

1.27

Source

Second facility certification

Actual

BREEAM Excellent

Source

Infrastructure & permits

Technical details (2)
Electric grid

Partially operational

60 MW

Up to 60 MW across four facilities; not current delivered total.

Electric grid

Operational

10 MW

Second facility only.

Public-source research. Plans may change. See Evidence for sources and qualifications.