DAMAC Digital Cikarang AI Data Center

Cikarang, West Java, IndonesiaPreconstruction
Capacity
144 MW
Planned / design
Lead participant
DAMAC Digital
Developer
Last updated
Aug 27, 2026
Most recent public record update

About DAMAC Digital Cikarang AI Data Center

DAMAC Digital acquired a 50,000-square-metre site in Cikarang, West Java for an AI-oriented data center campus. The planned investment exceeds $2.3 billion and the design calls for more than 144 MW of capacity.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design144 MWDesign · DAMAC Digital Cikarang AI Data Center
Design144 MWDesign · DAMAC Digital Cikarang AI Data Center

Development

1 phases · 2 milestones
Development programAnnounced Or Preconstruction

DAMAC Digital Cikarang AI Data Center: Preconstruction.

Jul 21, 2025
DAMAC Digital Cikarang AI Data Center: Development-stage campus following land acquisition.
In Progress
DAMAC Digital Cikarang AI Data Center — Preconstruction
In Progress

Infrastructure

Electric GridPlanned Or Represented

144 MW

144 MW planned or design IT capacity

Site FacilityPlanned Or Represented

AI-focused campus planned within the Cikarang industrial market.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
DAMAC Digital site | Cikarang | Bekasi | West Java | Indonesia
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
144 MW
Design
Capacity Basis
JLL states projected capacity exceeding 144 MW; stored as a floor.
Actual
Project Identity
DAMAC Digital Cikarang AI Data Center
Actual
Lifecycle Status
Preconstruction
Actual
Location
Cikarang, West Java, ID
Actual
Participant Roles
DAMAC Digital, JLL
Actual
Capacity
144 MW
Design
Capacity Basis
144 MW planned or design IT capacity
Actual
Development Scale
50,000-Square metre site; projected capacity above 144 MW
Actual
Infrastructure
AI-focused campus planned within the Cikarang industrial market.
Actual