Cartis diligence evidence schedule
CyrusOne SAT1 San Antonio Data Center
PRJ-0888 · Site · San Antonio, Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
CyrusOne SAT1 San Antonio Data Center, also known as CyrusOne SAT1, is a data center project in San Antonio, TX, US developed and operated by CyrusOne. San Antonio facility with 9 MW of total IT capacity and operator-described high-density colocation infrastructure. Resilient power and cooling, cloud and internet-exchange connectivity, and multilayer physical security.
Headline: 9 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · CyrusOne SAT1 | San Antonio | TX | US
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 63449 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Lifecycle status · Operational
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 63450 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Reported capacity · 9 MW
Design · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 63451 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Capacity basis · CyrusOne publishes 9 MW of critical IT capacity for this record boundary.
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 63452 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Location context · CyrusOne SAT1 | San Antonio | TX | US
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93225 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Lifecycle status · Operating
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93226 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Reported capacity · 9 MW
Planned / design or future potential · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93227 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Capacity basis · 9 MW facility or campus design capacity.
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93228 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne CyrusOne SAT1 profile
CyrusOne · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3556 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
https://www.cyrusone.com/data-centers/north-america/san-antonio-texas-sat1
Project boundary · CyrusOne SAT1
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93230 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne current global location index
CyrusOne · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5137 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers
https://www.cyrusone.com/data-centers
Location context · San Antonio, TX, US
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93231 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne current global location index
CyrusOne · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5137 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers
https://www.cyrusone.com/data-centers
Lifecycle status · Operating
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93232 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne current global location index
CyrusOne · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5137 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers
https://www.cyrusone.com/data-centers
Capacity basis · 9 MW facility or campus design capacity.
Actual · CyrusOne SAT1 San Antonio Data Center (Project)
Claim 93233 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne current global location index
CyrusOne · Document date: Aug 29, 2026 · Primary
Source reference: SRC-5137 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/data-centers
https://www.cyrusone.com/data-centers
Counterparties and capital
CyrusOne · Developer · CMP-0172
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.