Cartis diligence evidence schedule
CyrusOne MAD1 Madrid Data Center
PRJ-0834 · Site · Alcobendas, Community of Madrid, Spain
Record last updated Oct 28, 2026
Scope and capacity
CyrusOne MAD1 Madrid Data Center, also known as CyrusOne MAD1, is a data center project in Alcobendas, Community of Madrid, ES associated with CyrusOne. Five-acre site; one two-story building; 6,000 square metres of technical space; 18 MW total IT load. Madrid development with renewable-energy design, air-cooled closed-loop chillers and onsite solar generation. 18 MW is the operator-published future facility or full-build design boundary.
Headline: 18 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (13)
Location context · CyrusOne MAD1 | Alcobendas | Community of Madrid | ES
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 61883 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Lifecycle status · Construction
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 61884 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Reported capacity · 18 MW
Design · CyrusOne MAD1 Madrid Data Center (Project)
Claim 61885 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Capacity basis · CyrusOne publishes 18 MW of critical IT capacity for this record boundary.
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 61886 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Location context · CyrusOne MAD1 | Alcobendas | Community of Madrid | ES
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97185 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Lifecycle status · Construction
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97186 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Reported capacity · 18 MW
Planned / design or future potential · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97187 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Capacity basis · 18 MW is the operator published future facility or full build design boundary.
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97188 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne breaks ground on MAD1
CyrusOne · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3447 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
https://www.cyrusone.com/resources/press-releases/cyrusone-breaks-ground-on-first-spanish-data-center-in-madrid-as-european-expansion-continues
Project boundary · CyrusOne MAD1
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97190 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne Madrid 1 integrated environmental authorization notice
Community of Madrid · Document date: Apr 27, 2026 · Primary
Source reference: SRC-5346 · Government record · Recorded authority: Official primary
Source URL
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
Location context · Alcobendas, Community of Madrid, ES
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97191 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne Madrid 1 integrated environmental authorization notice
Community of Madrid · Document date: Apr 27, 2026 · Primary
Source reference: SRC-5346 · Government record · Recorded authority: Official primary
Source URL
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
Lifecycle status · Construction
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97192 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne Madrid 1 integrated environmental authorization notice
Community of Madrid · Document date: Apr 27, 2026 · Primary
Source reference: SRC-5346 · Government record · Recorded authority: Official primary
Source URL
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
Development detail · Five acre site; one two story building; 6,000 square metres of technical space; 18 MW total IT load.
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97193 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne Madrid 1 integrated environmental authorization notice
Community of Madrid · Document date: Apr 27, 2026 · Primary
Source reference: SRC-5346 · Government record · Recorded authority: Official primary
Source URL
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
Capacity basis · 18 MW is the operator published future facility or full build design boundary.
Actual · CyrusOne MAD1 Madrid Data Center (Project)
Claim 97194 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- CyrusOne Madrid 1 integrated environmental authorization notice
Community of Madrid · Document date: Apr 27, 2026 · Primary
Source reference: SRC-5346 · Government record · Recorded authority: Official primary
Source URL
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
https://www.bocm.es/boletin/CM_Orden_BOCM/2026/04/27/BOCM-20260427-47.PDF
Counterparties and capital
CyrusOne · Developer · CMP-0172
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.