Cartis diligence evidence schedule
CyrusOne LON6 Iver Heath
PRJ-0038 · Site · Dromenagh Farm / Sevenhills Road, Iver Heath, Buckinghamshire, United Kingdom
Record last updated Oct 28, 2026
Scope and capacity
CyrusOne's current LON6 operator page, checked October 28, 2026, advertises 108 MW of planned IT capacity and still describes the Iver Heath campus as in development. This differs from the 90 MW IT design in the June 13, 2025 announcement; it is not confirmation of commissioned capacity or a newly granted planning permission. The original permitted design comprised six structures and ten data halls. The planned Q3 2026 groundbreaking was not confirmed in this review.
Headline: 90 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (14)
Project status · Full planning permission; preconstruction
Permitted · CyrusOne LON6 Iver Heath (Project)
Claim 5269 · Recorded claim type: Permitted · Review: Approved · Claim date: Jun 17, 2025
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: Jun 30, 2025 · Corroborating
Source reference: SRC-0295 · Company announcement · Recorded authority: Party primary
Source URL
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
- 60,000sqm data centre approved for Iver Heath
Henley Standard · Document date: Jun 17, 2025 · Primary
Source reference: SRC-0293 · News report · Recorded authority: Secondary
Source URL
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
Target IT capacity · 90 MW
Planned / design or future potential · CyrusOne LON6 Iver Heath (Project)
Claim 5270 · Recorded claim type: Forecast · Review: Approved · Claim date: Jun 13, 2025
Headline treatment: Selected headline
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Corroborating
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
- CyrusOne announces plans for 90MW data center campus in Buckinghamshire, UK
Data Center Dynamics · Document date: Jun 13, 2025 · Corroborating
Source reference: SRC-0294 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Technical IT space · 30,000 sqm
Forecast · CyrusOne LON6 Iver Heath (Project)
Claim 5271 · Recorded claim type: Forecast · Review: Approved · Claim date: Jun 13, 2025
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Corroborating
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Data hall count · 10 count
Design · CyrusOne LON6 Iver Heath (Project)
Claim 5272 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Physical data center structures · 6 count
Design · Permitted LON6 full campus (Phase)
Claim 5273 · Recorded claim type: Design · Review: Approved · Claim date: Jun 13, 2025
- 60,000sqm data centre approved for Iver Heath
Henley Standard · Document date: Jun 17, 2025 · Corroborating
Source reference: SRC-0293 · News report · Recorded authority: Secondary
Source URL
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Primary
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
- CyrusOne announces plans for 90MW data center campus in Buckinghamshire, UK
Data Center Dynamics · Document date: Jun 13, 2025 · Corroborating
Source reference: SRC-0294 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
Utility supply design · 160 MVA
Design · CyrusOne LON6 Iver Heath (Project)
Claim 5274 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Grid feed voltage · 132 kV
Actual · CyrusOne LON6 Iver Heath (Project)
Claim 5275 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Planning permission · Full planning permission in place; conditions/phasing details remain
Permitted · Permitted LON6 full campus (Phase)
Claim 5276 · Recorded claim type: Permitted · Review: Approved · Claim date: Jun 30, 2025
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: Jun 30, 2025 · Corroborating
Source reference: SRC-0295 · Company announcement · Recorded authority: Party primary
Source URL
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
- 60,000sqm data centre approved for Iver Heath
Henley Standard · Document date: Jun 17, 2025 · Primary
Source reference: SRC-0293 · News report · Recorded authority: Secondary
Source URL
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
Planned investment · £>1200000000
Transaction scope · CyrusOne LON6 Iver Heath (Project)
Claim 5277 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Jun 13, 2025
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: Jun 30, 2025 · Corroborating
Source reference: SRC-0295 · Company announcement · Recorded authority: Party primary
Source URL
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Primary
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
Biodiversity net gain · 71 percent
Forecast · CyrusOne LON6 Iver Heath (Project)
Claim 5278 · Recorded claim type: Forecast · Review: Approved · Claim date: Jun 13, 2025
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Corroborating
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Planned tree planting · 670 count
Forecast · CyrusOne LON6 Iver Heath (Project)
Claim 5279 · Recorded claim type: Forecast · Review: Approved · Claim date: Jun 13, 2025
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Corroborating
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Public access green space · 18 acres
Forecast · CyrusOne LON6 Iver Heath (Project)
Claim 5280 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- Data Center — London, UK: LON6
CyrusOne · Document date: Not stated · Primary
Source reference: SRC-0290 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Initial power target · Mid 2027
Forecast · Initial power and first-capacity delivery (Phase)
Claim 5282 · Recorded claim type: Forecast · Review: Approved · Claim date: Jun 13, 2025
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Primary
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
- CyrusOne announces plans for 90MW data center campus in Buckinghamshire, UK
Data Center Dynamics · Document date: Jun 13, 2025 · Corroborating
Source reference: SRC-0294 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
First capacity target · Early 2028
Forecast · Initial power and first-capacity delivery (Phase)
Claim 5283 · Recorded claim type: Forecast · Review: Approved · Claim date: Jun 13, 2025
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: Jun 30, 2025 · Corroborating
Source reference: SRC-0295 · Company announcement · Recorded authority: Party primary
Source URL
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: Jun 13, 2025 · Primary
Source reference: SRC-0291 · Company announcement · Recorded authority: Party primary
Source URL
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
Counterparties and capital
Buckinghamshire Council · Government authority · CMP-0174
CyrusOne · Operator · CMP-0172
CyrusOne UK6 Limited · Owner · CMP-0173
Montagu Evans · Contractor · CMP-0177
Scottish and Southern Electricity Networks · Operator · CMP-0175
UK Government departments · Government authority · CMP-0178
£1,200,000,000 · Jun 13, 2025
More-than amount for local/national economic investment; financing structure and draw schedule undisclosed.
CyrusOne (Sponsor)
Sources (2)
Financing record 32; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.