Cartis diligence evidence schedule
CyrusOne LON6 Iver Heath
PRJ-0038 · Site · Dromenagh Farm / Sevenhills Road, Iver Heath, Buckinghamshire, United Kingdom
Captured 2026-09-06T04:13:12.254Z · Record last updated 2026-08-22
SHA-256: 8f15db63099afbd35445997494e7e1e4d5259c34a7814a7f8409588227d93df9
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
CyrusOne's LON6 campus in Iver Heath has planning permission for a 90 MW IT design across six structures and ten data halls. Its planned Q3 2026 groundbreaking was not confirmed by the cutoff.
Headline: 90 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Project Status · Full planning permission; preconstruction
permitted · CyrusOne LON6 Iver Heath (project)
Claim 5269 · Review: Approved · Claim date: 2025-06-17T00:00:00+00:00
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: 2025-06-30 · Corroborating
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW - 60,000sqm data centre approved for Iver Heath
Henley Standard · Document date: 2025-06-17 · Primary
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
Target It Capacity · 90 MW
Planned / design or future potential · CyrusOne LON6 Iver Heath (project)
Claim 5270 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
Headline treatment: Selected headline
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Corroborating
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core - CyrusOne announces plans for 90MW data center campus in Buckinghamshire, UK
Data Center Dynamics · Document date: 2025-06-13 · Corroborating
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/ - Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Technical It Space · 30,000 sqm
forecast · CyrusOne LON6 Iver Heath (project)
Claim 5271 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Corroborating
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core - Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Data Hall Count · 10 count
design · CyrusOne LON6 Iver Heath (project)
Claim 5272 · Review: Approved · Claim date: Not published
- Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Physical Data Center Structures · 6 count
design · Permitted LON6 full campus (phase)
Claim 5273 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
- 60,000sqm data centre approved for Iver Heath
Henley Standard · Document date: 2025-06-17 · Corroborating
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html - CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Primary
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core - CyrusOne announces plans for 90MW data center campus in Buckinghamshire, UK
Data Center Dynamics · Document date: 2025-06-13 · Corroborating
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
Utility Supply Design · 160 MVA
design · CyrusOne LON6 Iver Heath (project)
Claim 5274 · Review: Approved · Claim date: Not published
- Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Grid Feed Voltage · 132 kV
actual · CyrusOne LON6 Iver Heath (project)
Claim 5275 · Review: Approved · Claim date: Not published
- Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Planning Permission · Full planning permission in place; conditions/phasing details remain
permitted · Permitted LON6 full campus (phase)
Claim 5276 · Review: Approved · Claim date: 2025-06-30T00:00:00+00:00
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: 2025-06-30 · Corroborating
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW - 60,000sqm data centre approved for Iver Heath
Henley Standard · Document date: 2025-06-17 · Primary
https://www.henleystandard.co.uk/news/planning/201771/60-000sqm-data-centre-approved-for-iver-heath.html
Planned Investment · £>1200000000
Planned / design or future potential · CyrusOne LON6 Iver Heath (project)
Claim 5277 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: 2025-06-30 · Corroborating
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW - CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Primary
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
Biodiversity Net Gain · 71 percent
forecast · CyrusOne LON6 Iver Heath (project)
Claim 5278 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Corroborating
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core - Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Planned Tree Planting · 670 count
Planned / design or future potential · CyrusOne LON6 Iver Heath (project)
Claim 5279 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Corroborating
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core - Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Public Access Green Space · 18 acres
forecast · CyrusOne LON6 Iver Heath (project)
Claim 5280 · Review: Approved · Claim date: Not published
- Data Center — London, UK: LON6
CyrusOne · Document date: Not published · Primary
https://www.cyrusone.com/data-centers/emea/london-uk-lon6
Initial Power Target · 2027-06
Planned / design or future potential · Initial power and first-capacity delivery (phase)
Claim 5282 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Primary
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core - CyrusOne announces plans for 90MW data center campus in Buckinghamshire, UK
Data Center Dynamics · Document date: 2025-06-13 · Corroborating
https://www.datacenterdynamics.com/en/news/cyrusone-announces-plans-for-90mw-data-center-campus-in-buckinghamshire-uk/
First Capacity Target · 2028-Q1
Planned / design or future potential · Initial power and first-capacity delivery (phase)
Claim 5283 · Review: Approved · Claim date: 2025-06-13T00:00:00+00:00
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire
Montagu Evans · Document date: 2025-06-30 · Corroborating
https://www.linkedin.com/posts/montagu-evans_go-ahead-for-our-client-leading-global-centre-activity-7346853175326326784-DqOW - CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core
CyrusOne · Document date: 2025-06-13 · Primary
https://www.cyrusone.com/resources/press-releases/cyrusone-plans-pioneering-new-london-facility-with-sustainability-at-its-core
Counterparties and capital
Buckinghamshire Council · Government Authority · CMP-0174
CyrusOne · Operator · CMP-0172
CyrusOne UK6 Limited · Owner · CMP-0173
Montagu Evans · Contractor · CMP-0177
Scottish and Southern Electricity Networks · Operator · CMP-0175
UK Government departments · Government Authority · CMP-0178
£1,200,000,000 · 2025-06-13
More-than amount for local/national economic investment; financing structure and draw schedule undisclosed.
CyrusOne (Sponsor)
Financing record 32; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.