CyrusOne LON6 Iver Heath
- Planned critical IT
- 90 MW
- Updated
- Oct 28, 2026
CyrusOne's current LON6 operator page, checked October 28, 2026, advertises 108 MW of planned IT capacity and still describes the Iver Heath campus as in development. This differs from the 90 MW IT design in the June 13, 2025 announcement; it is not confirmation of commissioned capacity or a newly granted planning permission. The original permitted design comprised six structures and ten data halls. The planned Q3 2026 groundbreaking was not confirmed in this review.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
6 buildings
Six physical structures containing ten 9 MW data halls; no construction start established.
Delivery sub-phase is not quantified in MW.
Milestones (4)
Jun 12, 2025 · Recorded actual event
Completed · Permit approved
Source not linkedQ3 2026 · Forecast / planned record
Forecast · Forecast completion
Source not linked2027 · Forecast / planned record
Forecast · Forecast completion
Source not linked2028 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Operator
Sources by role
Operator (1)
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core · Jun 13, 2025 · Corroborating
Operator (1)
- Data Center — London, UK: LON6 · Primary
Owner
Sources by role
Owner (1)
- 60,000sqm data centre approved for Iver Heath · Jun 17, 2025 · Primary
Operator
Sources by role
Operator (1)
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core · Jun 13, 2025 · Corroborating
Operator (1)
- Data Center — London, UK: LON6 · Primary
Other participants (3)
Government authority
Sources by role
Government authority (1)
- 60,000sqm data centre approved for Iver Heath · Jun 17, 2025 · Primary
Contractor
Sources by role
Contractor (1)
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire · Jun 30, 2025 · Corroborating
Contractor (1)
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core · Jun 13, 2025 · Primary
Government authority
Sources by role
Government authority (1)
- CyrusOne Plans Pioneering New London Facility with Sustainability At Its Core · Jun 13, 2025 · Primary
Capital & incentives
Capital claims and financing records may overlap. Their amounts are not added together.
Capital claims
Financing records
Investment commitment
£1,200,000,000Jun 13, 2025
More-than amount for local/national economic investment; financing structure and draw schedule undisclosed.
Parties & sources
CyrusOne (Sponsor)
Sources (2)
Incentives
Incentive
Status not stated · UK Government departments
HM Treasury, DBT, DSIT and Office for Investment support was described as critical; no cash, tax rate, term or formal award is attached.
Technical specifications
Additional project facts
Planning permission
PermittedFull planning permission in place; conditions/phasing details remain
Permitted LON6 full campus · Phase
SourceInfrastructure & permits
Technical details (4)
Planned or represented
160 MVA
grid supply — 160 MVA; design.
Planned or represented
64 percent regulated office energy
rooftop solar — 64 percent_regulated_office_energy; design target.
Planned or represented
heat export; design capability.
Planned or represented
air cooled free cooling; design.
Project map
Building · Documented
CyrusOne LON6 / Iver Heath Data Park
Buckinghamshire Council
Jun 12, 2025
Sources (2)
- CyrusOne gets approval for £1.2 billion data centre in Buckinghamshire · Jun 30, 2025 · Corroborating
- 60,000sqm data centre approved for Iver Heath · Jun 17, 2025 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.