Cartis diligence evidence schedule
CyrusOne HOU3–HOU4 Houston Data Center Campus
PRJ-0877 · Site · Houston, Texas, United States
Captured 2026-09-06T04:13:43.363Z · Record last updated 2026-08-30
SHA-256: d61154535d5940407c9962240bd71b357619611c444d5358487eafc22d671587
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
CyrusOne HOU3–HOU4 Houston Data Center Campus, also known as CyrusOne Houston Campus, is a partially operational data center campus in Houston, TX, US associated with CyrusOne. Dual-facility campus; 347,000 square feet of technical space; 84 MW total IT capacity. Dual-facility technology-corridor campus with closed-loop cooling, extensive backup generation and layered security.
Headline: 84 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Location Context · CyrusOne HOU3–HOU4 | Houston | TX | US
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 63405 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne HOU3–HOU4 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Lifecycle Status · Operational
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 63406 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne HOU3–HOU4 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Reported Capacity · 84 MW
design · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 63407 · Review: Approved · Claim date: Not published
Headline treatment: Separate claim, not added to the headline
- CyrusOne CyrusOne HOU3–HOU4 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Capacity Basis · CyrusOne publishes 84 MW of critical IT capacity for this record boundary.
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 63408 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne HOU3–HOU4 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Location Context · CyrusOne HOU3–HOU4 | Houston | TX | US
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 93127 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne HOU3–HOU4 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Lifecycle Status · Operating
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 93128 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne HOU3–HOU4 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Technical Area · 347,000 square feet
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 93131 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne HOU3–HOU4 profile
CyrusOne · Document date: 2026-08-28 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Facility Count · 2 facilities
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 93134 · Review: Approved · Claim date: Not published
- CyrusOne current global location index
CyrusOne · Document date: 2026-08-29 · Primary
https://www.cyrusone.com/data-centers
Built Out In 2024 · HOU4
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 93135 · Review: Approved · Claim date: Not published
- CyrusOne current global location index
CyrusOne · Document date: 2026-08-29 · Primary
https://www.cyrusone.com/data-centers
Location Context · CyrusOne Houston Campus | Houston | TX | US
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104282 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne Houston Campus profile
CyrusOne · Document date: 2026-08-27 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Lifecycle Status · Partially operational
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104283 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne Houston Campus profile
CyrusOne · Document date: 2026-08-27 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Reported Capacity · 84 MW
Planned / design or future potential · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104284 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- CyrusOne CyrusOne Houston Campus profile
CyrusOne · Document date: 2026-08-27 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Capacity Basis · 84 MW facility or campus IT design capacity.
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104285 · Review: Approved · Claim date: Not published
- CyrusOne CyrusOne Houston Campus profile
CyrusOne · Document date: 2026-08-27 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Campus It Design · 84 MW
Planned / design or future potential · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104286 · Review: Approved · Claim date: Not published
Headline treatment: Separate claim, not added to the headline
- CyrusOne CyrusOne Houston Campus profile
CyrusOne · Document date: 2026-08-27 · Primary
https://www.cyrusone.com/data-centers/north-america/houston-tx
Technical Area · 347,000 square feet
design · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104287 · Review: Approved · Claim date: Not published
- CyrusOne sustainability reporting
CyrusOne · Document date: 2026-08-30 · Primary
https://www.cyrusone.com/resources/sustainability-report
Hou3 Fitout Area · 250,000 square feet
actual · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104288 · Review: Approved · Claim date: Not published
- CyrusOne sustainability reporting
CyrusOne · Document date: 2026-08-30 · Primary
https://www.cyrusone.com/resources/sustainability-report
Hou3 Fitout Cost · $57,000,000
transaction scope · CyrusOne HOU3–HOU4 Houston Data Center Campus (project)
Claim 104289 · Review: Approved · Claim date: Not published
- CyrusOne sustainability reporting
CyrusOne · Document date: 2026-08-30 · Primary
https://www.cyrusone.com/resources/sustainability-report
Counterparties and capital
CyrusOne · Developer · CMP-0172
$57,000,000 · 2022-08-03
TDLR estimate for the HOU3 fit-out, not total campus investment or a financing close.
CyrusOne (Borrower)
Financing record 202; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.