Skip to content
All records
Data center siteSite record

CyrusOne FRA6 Frankfurt Data Center Campus

Frankfurt-Sossenheim, HE, GermanyUnder construction
Capacity
72 MW
Planned / design
Lead participant
CyrusOne
Developer
Last updated
Aug 30, 2026
Most recent public record update

About CyrusOne FRA6 Frankfurt Data Center Campus

CyrusOne FRA6 Frankfurt Data Center Campus, also known as CyrusOne FRA6, is a construction data center campus in Frankfurt, HE, DE associated with CyrusOne. Four-story development; eight data halls; 20,800 square metres; 72 MW planned IT capacity. Frankfurt campus with active/active 108 MVA supply, free-cooling chillers and 100% renewable-energy design. 72 MW is the documented future facility or campus design. It is not energized or operating IT load.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load72 MWDesign · CyrusOne FRA6 Frankfurt Data Center Campus
Future Potential72 MWDesign · CyrusOne FRA6 Frankfurt Data Center Campus
Future Potential72 MWDesign · CyrusOne FRA6 Frankfurt Data Center Campus
It Load72 MWForecast · CyrusOne FRA6 Frankfurt Data Center Campus

Development

2 phases · 3 milestones
Development, permitting and phased deliveryAnnounced Or Preconstruction

72 MW is the operator-published future facility or full-build design boundary. It is not operating IT load.

Development, permitting and phased deliveryUnder Construction

72 MW is the documented future facility or campus design. It is not energized or operating IT load.

Aug 27, 2026
Primary project source reviewed for CyrusOne FRA6
Completed
Aug 28, 2026
Current source record reviewed for CyrusOne FRA6
Completed
Aug 30, 2026
Operating status not inferred from development evidence
Completed

Infrastructure

Electric GridPlanned Or Represented

Planned 108 MVA active-active supply, closed-loop cooling, waste-heat readiness and multilayer security.

Cooling SystemPlanned Or Represented

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Electric GridPlanned Or Represented

Frankfurt campus with active/active 108 MVA supply, free-cooling chillers and 100% renewable-energy design.

Cooling SystemPlanned Or Represented

Cooling and efficiency claims remain limited to source-defined designs; no delivered load or water use is inferred.

Project map

0 of 1 project point mapped
Infrastructure facts
4
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 2Cooling & water: 2

Facts & sources

Published claims and their source links.

23 facts
Location Context
CyrusOne FRA6 | Frankfurt-Sossenheim | HE | DE
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
72 MW
Design
Capacity Basis
CyrusOne publishes 72 MW of critical IT capacity for this record boundary.
Actual
Location Context
CyrusOne FRA6 | Frankfurt-Sossenheim | HE | DE
Actual
Lifecycle Status
Preconstruction
Actual
Reported Capacity
72 MW
Design
Capacity Basis
72 MW is the operator published future facility or full build design boundary.
Actual
Project Boundary
CyrusOne FRA6
Actual
Location Context
Frankfurt-Sossenheim, HE, DE
Actual
Lifecycle Status
Preconstruction
Actual
Development Detail
6.8-Acre Europark site; one four story facility; eight data halls; 20,800 square metres of technical space; 72 MW IT capacity.
Actual
Capacity Basis
72 MW is the operator published future facility or full build design boundary.
Actual
Location Context
CyrusOne FRA6 | Frankfurt | HE | DE
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
72 MW
Design
Capacity Basis
72 MW is the documented future facility or campus design. It is not energized or operating IT load.
Actual
Reported Capacity
72 MW
Forecast
Project Identity
CyrusOne FRA6
Actual
Location Context
Frankfurt, HE, DE
Actual
Lifecycle Status
Construction
Actual
Development Detail
Four story development; eight data halls; 20,800 square metres; 72 MW planned IT capacity.
Actual
Capacity Basis
72 MW is the documented future facility or campus design. It is not energized or operating IT load.
Actual