CyrusOne FRA6 Frankfurt Data Center Campus
- Planned critical IT
- 72 MW
- Updated
- Oct 28, 2026
CyrusOne’s current FRA6 plan specifies 84 MW of future IT capacity across seven data halls and 14,783 square metres of technical space. This updates the earlier 72 MW, eight-hall design; neither figure represents operating IT load. CyrusOne FRA6 Frankfurt Data Center Campus, also known as CyrusOne FRA6, is a construction data center campus in Frankfurt, HE, DE associated with CyrusOne. The earlier design described a four-story development with eight data halls, 20,800 square metres and 72 MW planned IT capacity. Frankfurt campus with active/active 108 MVA supply, free-cooling chillers and 100% renewable-energy design. 72 MW is retained as the earlier documented future facility or campus design. It is not energized or operating IT load.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
72 MW is the operator-published future facility or full-build design boundary. It is not operating IT load.
72 MW is the documented future facility or campus design. It is not energized or operating IT load.
Milestones (1)
Aug 30, 2026 · Recorded actual event
Completed · Status changed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- CyrusOne CyrusOne FRA6 profile · Aug 28, 2026 · Primary
Site & development
Additional project facts
Capacity basis
ActualCyrusOne publishes 72 MW of critical IT capacity for this record boundary.
SourceCapacity basis
Actual72 MW is the operator published future facility or full build design boundary.
SourceCapacity basis
Actual72 MW is the operator published future facility or full build design boundary.
SourceCapacity basis
Actual72 MW is the documented future facility or campus design. It is not energized or operating IT load.
SourceCapacity basis
Actual72 MW is the documented future facility or campus design. It is not energized or operating IT load.
SourceInfrastructure & permits
Technical details (4)
Planned or represented
Planned 108 MVA active-active supply, closed-loop cooling, waste-heat readiness and multilayer security.
Planned or represented
Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.
Planned or represented
Frankfurt campus with active/active 108 MVA supply, free-cooling chillers and 100% renewable-energy design.
Planned or represented
Cooling and efficiency claims remain limited to source-defined designs; no delivered load or water use is inferred.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.
Related projects (4)
Partially operational · Frankfurt-Sossenheim, Hesse, Germany
Same locality: Frankfurt-Sossenheim · Shared participant: CyrusOne
Compare in a collectionOperating · Frankfurt, Hesse, Germany
Shared participant: CyrusOne · Same market: Hesse, Germany
Compare in a collectionOperating · Frankfurt, Hesse, Germany
Shared participant: CyrusOne · Same market: Hesse, Germany
Compare in a collectionOperating · Frankfurt, Hesse, Germany
Shared participant: CyrusOne · Same market: Hesse, Germany
Compare in a collection