Skip to content
All records
Data center siteSite record

CyrusOne FRA1 Frankfurt Data Center

Frankfurt, HE, GermanyOperating / Stabilized
Capacity
9.1 MW
Planned critical IT
Lead participant
CyrusOne
Developer
Last updated
Aug 28, 2026
Most recent public record update

About CyrusOne FRA1 Frankfurt Data Center

CyrusOne FRA1 Frankfurt Data Center, also known as CyrusOne FRA1, is a data center project in Frankfurt, HE, DE developed and operated by CyrusOne. Frankfurt facility with 9.1 MW of published IT capacity and operator-described enterprise-grade technical space. Resilient electrical and cooling infrastructure with carrier-neutral connectivity in the Frankfurt market. CyrusOne currently rounds FRA1 to 9 MW; an earlier facility sheet states 9.1 MW. The current rounded design boundary is presented with the earlier exact figure retained as context.

Projects sharing a market, utility, or organization.

4 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load9.1 MWDesign · CyrusOne FRA1 Frankfurt Data Center
Design9 MWDesign · CyrusOne FRA1 Frankfurt Data Center

Development

1 phases · 1 milestones
Operating facility and documented expansionOperational

CyrusOne currently rounds FRA1 to 9 MW; an earlier facility sheet states 9.1 MW. Cartis publishes the current rounded design boundary and retains the exact legacy figure as context.

Aug 28, 2026
Current source record reviewed for CyrusOne FRA1
Completed

Infrastructure

Electric GridEnergized

Resilient electrical and cooling infrastructure with carrier-neutral connectivity in the Frankfurt market.

Cooling SystemOperational

CyrusOne describes closed-loop or air-cooled systems; the profile does not infer facility water use beyond the cited site specification.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
CyrusOne FRA1 | Frankfurt | HE | DE
Actual
Lifecycle Status
Operational
Actual
Reported Capacity
9.1 MW
Design
Capacity Basis
CyrusOne publishes 9.1 MW of critical IT capacity for this record boundary.
Actual
Location Context
CyrusOne FRA1 | Frankfurt | HE | DE
Actual
Lifecycle Status
Operating
Actual
Reported Capacity
9 MW
Design
Capacity Basis
CyrusOne currently rounds FRA1 to 9 MW; an earlier facility sheet states 9.1 MW. Cartis publishes the current rounded design boundary and retains the exact legacy figure as context.
Actual
Project Boundary
CyrusOne FRA1
Actual
Location Context
Frankfurt, HE, DE
Actual
Lifecycle Status
Operating
Actual
Capacity Basis
CyrusOne currently rounds FRA1 to 9 MW; an earlier facility sheet states 9.1 MW. Cartis publishes the current rounded design boundary and retains the exact legacy figure as context.
Actual