CyrusOne DUB1 Dublin Data Center Campus

PRJ-0850 · Site · Grange Castle, Dublin, County Dublin, Ireland

Captured 2026-09-06T22:54:05.397Z · Record last updated 2026-08-30

SHA-256: d6eacabe4baa82dcde4ced99cbbee9a098e67e7f6e84a9c56217b2f7aebce8b8

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

CyrusOne DUB1 Dublin Data Center Campus, also known as CyrusOne DUB1, is a partially operational data center campus in Dublin, Leinster, IE associated with CyrusOne. Three two-story buildings; 22,854 square metres; potential 54 MW total IT capacity. Carrier-neutral Dublin campus with dual redundant power and renewable-energy sourcing. 54 MW is the potential three-building campus total. The first building is complete, but a phase-specific operating IT figure is not published.

Headline: 54 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Location Context · CyrusOne DUB1 | Grange Castle, Dublin | County Dublin | IE

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 62622 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Lifecycle Status · Operational

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 62623 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Reported Capacity · 54 MW

design · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 62624 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Capacity Basis · CyrusOne publishes 54 MW of critical IT capacity for this record boundary.

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 62625 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Location Context · CyrusOne DUB1 | Grange Castle, Dublin | County Dublin | IE

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 97341 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Lifecycle Status · Partially operational

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 97342 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Reported Capacity · 54 MW

Planned / design or future potential · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 97343 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Capacity Basis · CyrusOne currently describes 54 MW as the campus potential across three buildings. Earlier launch material cited 74 MW total power; Cartis publishes 54 MW only as a future IT envelope, not current operating load.

Planned / design or future potential · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 97344 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Building Count · 3

design · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 97345 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Technical Area · 22,854 square metres

design · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 97346 · Review: Approved · Claim date: Not published

  1. CyrusOne Dublin data-center environmental impact assessment material

    Irish Environmental Protection Agency / South Dublin County Council · Document date: 2025-01-01 · Primary

    https://epawebapp.epa.ie/licences/lic_eDMS/090151b280821e0f.pdf

Utility Supply · 80 MVA

design · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 97348 · Review: Approved · Claim date: Not published

  1. CyrusOne Dublin data-center environmental impact assessment material

    Irish Environmental Protection Agency / South Dublin County Council · Document date: 2025-01-01 · Primary

    https://epawebapp.epa.ie/licences/lic_eDMS/090151b280821e0f.pdf

Location Context · CyrusOne DUB1 | Dublin | Leinster | IE

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104308 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Lifecycle Status · Partially operational

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104309 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Reported Capacity · 54 MW

Planned / design or future potential · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104310 · Review: Approved · Claim date: Not published

Headline treatment: Separate claim, not added to the headline

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Capacity Basis · 54 MW is the potential three building campus total. The first building is complete, but a phase specific operating IT figure is not published.

Planned / design or future potential · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104311 · Review: Approved · Claim date: Not published

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Full Build Potential · 54 MW

Planned / design or future potential · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104312 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. CyrusOne CyrusOne DUB1 profile

    CyrusOne · Document date: 2026-08-28 · Primary

    https://www.cyrusone.com/data-centers/emea/dublin-ireland

Building Count · 3

design · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104313 · Review: Approved · Claim date: Not published

  1. CyrusOne sustainability reporting

    CyrusOne · Document date: 2026-08-30 · Primary

    https://www.cyrusone.com/resources/sustainability-report

Development Area · 35,426 square metres

design · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104314 · Review: Approved · Claim date: Not published

  1. CyrusOne sustainability reporting

    CyrusOne · Document date: 2026-08-30 · Primary

    https://www.cyrusone.com/resources/sustainability-report

First Building · Completed; operating MW not disclosed

actual · CyrusOne DUB1 Dublin Data Center Campus (project)

Claim 104315 · Review: Approved · Claim date: Not published

  1. CyrusOne sustainability reporting

    CyrusOne · Document date: 2026-08-30 · Primary

    https://www.cyrusone.com/resources/sustainability-report

Counterparties and capital

CyrusOne · Developer · CMP-0172

EirGrid · Utility Provider · CMP-0721

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.