Cartis diligence evidence schedule

CyrusOne CIN5 Lebanon Data Center Campus

PRJ-0839 · Site · Lebanon, Ohio, United States

Record last updated Oct 28, 2026

Scope and capacity

CyrusOne CIN5 Lebanon Data Center Campus, also known as CyrusOne CIN5, is a data center project in Lebanon, OH, US associated with CyrusOne. 123-acre campus; 400,000 square feet of technical IT space; 12 MW IT capacity; additional build-to-suit land. Cincinnati-region campus with high-performance-computing capability, efficient cooling and multiple security layers.

Headline: 12 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · CyrusOne CIN5 | Lebanon | OH | US

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 61903 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Lifecycle status · Operational

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 61904 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Reported capacity · 12 MW

Design · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 61905 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Capacity basis · CyrusOne publishes 12 MW of total IT capacity for CIN5.

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 61906 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Location context · CyrusOne CIN5 | Lebanon | OH | US

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97234 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Lifecycle status · Operating

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97235 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Reported capacity · 12 MW

Planned / design or future potential · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97236 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Capacity basis · 12 MW facility or campus design capacity.

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97237 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne CyrusOne CIN5 profile

    CyrusOne · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3453 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.cyrusone.com/data-centers/north-america/lebanon-ohio

Project boundary · CyrusOne CIN5

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97239 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne Ohio facts

    CyrusOne · Document date: Mar 25, 2024 · Primary

    Source reference: SRC-5355 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://documents.cyrusone.com/wp-content/uploads/2024/03/CyrusOne-Ohio-Facts-032524.pdf

Location context · Lebanon, OH, US

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97240 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne Ohio facts

    CyrusOne · Document date: Mar 25, 2024 · Primary

    Source reference: SRC-5355 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://documents.cyrusone.com/wp-content/uploads/2024/03/CyrusOne-Ohio-Facts-032524.pdf

Lifecycle status · Operating

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97241 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne Ohio facts

    CyrusOne · Document date: Mar 25, 2024 · Primary

    Source reference: SRC-5355 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://documents.cyrusone.com/wp-content/uploads/2024/03/CyrusOne-Ohio-Facts-032524.pdf

Development detail · 123-Acre campus; 400,000 square feet of technical IT space; 12 MW IT capacity; additional build to suit land.

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97242 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne Ohio facts

    CyrusOne · Document date: Mar 25, 2024 · Primary

    Source reference: SRC-5355 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://documents.cyrusone.com/wp-content/uploads/2024/03/CyrusOne-Ohio-Facts-032524.pdf

Capacity basis · 12 MW facility or campus design capacity.

Actual · CyrusOne CIN5 Lebanon Data Center Campus (Project)

Claim 97243 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CyrusOne Ohio facts

    CyrusOne · Document date: Mar 25, 2024 · Primary

    Source reference: SRC-5355 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://documents.cyrusone.com/wp-content/uploads/2024/03/CyrusOne-Ohio-Facts-032524.pdf

Counterparties and capital

CyrusOne · Developer · CMP-0172

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.