CyrusOne CHI5 Lombard Data Center

Lombard, Illinois, United StatesOperating / Stabilized
Capacity
12 MW
Planned critical IT
Lead participant
CyrusOne
Developer
Last updated
Aug 28, 2026
Most recent public record update

About CyrusOne CHI5 Lombard Data Center

CyrusOne CHI5 Lombard Data Center, also known as CyrusOne CHI5, is a data center project in Lombard, IL, US associated with CyrusOne. Chicago-area facility with 60,000 square feet of technical IT space and 12 MW of total IT capacity.

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load12 MWDesign · CyrusOne CHI5 Lombard Data Center
Design12 MWDesign · CyrusOne CHI5 Lombard Data Center

Development

1 phases · 1 milestones
Operating facility and documented expansionOperational

12 MW is the operator-published facility or campus design boundary. It is not measured tenant utilization or live IT draw.

Aug 27, 2026
Current source record reviewed for CyrusOne CHI5
Completed

Infrastructure

Electric GridEnergized

Enterprise facility with diverse utility feeds, high-capacity Chicago connectivity and N+1 cooling.

Cooling SystemOperational

Operator describes resilient cooling; Public sources do not establish water use or delivered capacity beyond the cited project specification.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

13 facts
Location Context
CyrusOne CHI5 | Lombard | IL | US
Actual
Lifecycle Status
Operational
Actual
Reported Capacity
12 MW
Design
Capacity Basis
CyrusOne publishes 12 MW of total IT capacity for CHI5.
Actual
Location Context
CyrusOne CHI5 | Lombard | IL | US
Actual
Lifecycle Status
Operating
Actual
Reported Capacity
12 MW
Design
Capacity Basis
12 MW facility or campus design capacity.
Actual
Project Boundary
CyrusOne CHI5
Actual
Location Context
Lombard, IL, US
Actual
Lifecycle Status
Operating
Actual
Development Detail
Chicago area facility; 60,000 square feet of technical IT space; 12 MW total IT capacity.
Actual
Capacity Basis
12 MW facility or campus design capacity.