Crow Holdings Fayetteville Data Center Proposal

PRJ-0553 · Site · Highway 85 North, north of Fayette Pavilion, Georgia, United States

Record last updated Oct 28, 2026

Scope and capacity

Crow Holdings Development and CHI/Acquisitions proposed a single data center building north of Fayette Pavilion. The Planning & Zoning Commission denied the site plan, the applicants withdrew their appeal, and Fayetteville now prohibits new data centers in every zoning district.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location · North of Fayette Pavilion along Highway 85 North, Fayetteville, Georgia

Proposal · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50535 · Recorded claim type: Proposal · Review: Approved · Claim date: Mar 18, 2026

  1. Data Center Discussion

    City of Fayetteville, Georgia · Document date: Not stated · Primary

    Source reference: SRC-0656 · Government record · Recorded authority: Official primary

    Source URL

    https://www.fayetteville-ga.gov/746/Data-Center-Discussion

Site area · 37.4 acres

Proposal · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50536 · Recorded claim type: Proposal · Review: Approved · Claim date: Mar 20, 2026

  1. Developer effectively withdraws application for data center in Fayetteville, Georgia

    Data Center Dynamics · Document date: Mar 20, 2026 · Primary

    Source reference: SRC-2664 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/developer-effectively-withdraws-application-for-data-center-in-fayetteville-georgia/

Building area · 300,000 sq. ft.

Proposal · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50537 · Recorded claim type: Proposal · Review: Approved · Claim date: Mar 20, 2026

  1. Developer effectively withdraws application for data center in Fayetteville, Georgia

    Data Center Dynamics · Document date: Mar 20, 2026 · Primary

    Source reference: SRC-2664 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/developer-effectively-withdraws-application-for-data-center-in-fayetteville-georgia/

Building count · 1 two story building

Proposal · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50538 · Recorded claim type: Proposal · Review: Approved · Claim date: Mar 20, 2026

  1. Developer effectively withdraws application for data center in Fayetteville, Georgia

    Data Center Dynamics · Document date: Mar 20, 2026 · Primary

    Source reference: SRC-2664 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/developer-effectively-withdraws-application-for-data-center-in-fayetteville-georgia/

Substation · One proposed substation

Proposal · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50539 · Recorded claim type: Proposal · Review: Approved · Claim date: Mar 20, 2026

  1. Developer effectively withdraws application for data center in Fayetteville, Georgia

    Data Center Dynamics · Document date: Mar 20, 2026 · Primary

    Source reference: SRC-2664 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/developer-effectively-withdraws-application-for-data-center-in-fayetteville-georgia/

Site plan decision · Denied by Planning & Zoning Commission

Actual · Site plan and appeal (Phase)

Claim 50541 · Recorded claim type: Actual · Review: Approved · Claim date: Mar 18, 2026

  1. Data Center Discussion

    City of Fayetteville, Georgia · Document date: Not stated · Primary

    Source reference: SRC-0656 · Government record · Recorded authority: Official primary

    Source URL

    https://www.fayetteville-ga.gov/746/Data-Center-Discussion

Appeal status · Officially withdrawn

Actual · Site plan and appeal (Phase)

Claim 50543 · Recorded claim type: Actual · Review: Approved · Claim date: Mar 18, 2026

  1. Data Center Discussion

    City of Fayetteville, Georgia · Document date: Not stated · Primary

    Source reference: SRC-0656 · Government record · Recorded authority: Official primary

    Source URL

    https://www.fayetteville-ga.gov/746/Data-Center-Discussion

Zoning context · New data centers prohibited in every City of Fayetteville zoning district

Permitted · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50544 · Recorded claim type: Permitted · Review: Approved · Claim date: Mar 18, 2026

  1. Data Center Discussion

    City of Fayetteville, Georgia · Document date: Not stated · Primary

    Source reference: SRC-0656 · Government record · Recorded authority: Official primary

    Source URL

    https://www.fayetteville-ga.gov/746/Data-Center-Discussion

Cryptomining use · Prohibited in supporting documentation

Proposal · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50545 · Recorded claim type: Proposal · Review: Approved · Claim date: Mar 20, 2026

  1. Developer effectively withdraws application for data center in Fayetteville, Georgia

    Data Center Dynamics · Document date: Mar 20, 2026 · Primary

    Source reference: SRC-2664 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/developer-effectively-withdraws-application-for-data-center-in-fayetteville-georgia/

Current status · Cancelled after denial and appeal withdrawal

Actual · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50546 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 13, 2026

  1. Data Center Discussion

    City of Fayetteville, Georgia · Document date: Not stated · Primary

    Source reference: SRC-0656 · Government record · Recorded authority: Official primary

    Source URL

    https://www.fayetteville-ga.gov/746/Data-Center-Discussion

Boundary exclusion · Distinct from the operating QTS Fayetteville campus on Highway 54 West

Actual · Crow Holdings Fayetteville Data Center Proposal (Project)

Claim 50547 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 13, 2026

  1. Data Center Discussion

    City of Fayetteville, Georgia · Document date: Not stated · Primary

    Source reference: SRC-0656 · Government record · Recorded authority: Official primary

    Source URL

    https://www.fayetteville-ga.gov/746/Data-Center-Discussion

Counterparties and capital

CHI/Acquisitions, LP · Developer · CMP-1269

City of Fayetteville · Government authority · CMP-1060

Crow Holdings Development · Developer · CMP-1268

Fayetteville Planning & Zoning Commission · Government authority · CMP-1270