Cartis diligence evidence schedule
Compass Meridian Campus
PRJ-0599 · Site · Meridian, Mississippi, United States
Record last updated Oct 28, 2026
Scope and capacity
Compass broke ground in 2025 on an eight-building data center campus in Meridian, Mississippi. Each building is designed for 40 MW of critical IT load, producing a planned campus total of 320 MW. The approximately $10 billion development is supported by Mississippi Power and state and local development programs.
Headline: 320 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · Compass Meridian campus | Meridian | Mississippi | United States
Actual · Compass Meridian Campus (Project)
Claim 54705 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Lifecycle status · Construction
Actual · Compass Meridian Campus (Project)
Claim 54706 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Reported capacity · 320 MW
Design · Compass Meridian Campus (Project)
Claim 54707 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Capacity basis · Eight buildings at 40 MW critical IT each
Actual · Compass Meridian Campus (Project)
Claim 54708 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Project identity · Compass Meridian Campus
Actual · Compass Meridian Campus (Project)
Claim 119557 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Lifecycle status · Construction program
Actual · Compass Meridian Campus (Project)
Claim 119558 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Location · Meridian, Lauderdale County, MS, US
Actual · Compass Meridian Campus (Project)
Claim 119559 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Participant roles · Compass Datacenters
Actual · Compass Meridian Campus (Project)
Claim 119560 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Capacity · 320 MW
Design · Compass Meridian Campus (Project)
Claim 119561 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Capacity basis · 320 MW planned critical IT design capacity
Planned / design or future potential · Compass Meridian Campus (Project)
Claim 119562 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Development scale · Compass broke ground in 2025 on an eight building data center campus in Meridian, Mississippi. Each building is designed for 40 MW of critical IT load, producing a planned campus total of 320 MW
Actual · Compass Meridian Campus (Project)
Claim 119563 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Infrastructure · The approximately $10 billion development is supported by Mississippi Power and state and local development programs.
Actual · Compass Meridian Campus (Project)
Claim 119564 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Compass announces $10 billion Lauderdale County investment
Compass Datacenters · Document date: May 12, 2025 · Corroborating
Source reference: SRC-6533 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
https://www.compassdatacenters.com/news/compass-10b-investment-lauderdale-county-mississippi/
- Compass data center markets — Meridian
Compass Datacenters · Document date: Not stated · Primary
Source reference: SRC-2941 · Company announcement · Recorded authority: Party primary
Source URL
https://www.compassdatacenters.com/data-center-markets/
https://www.compassdatacenters.com/data-center-markets/
Counterparties and capital
Compass Datacenters · Developer · CMP-0699
$10,000,000,000 · May 12, 2025
Announced campus investment.
Compass Datacenters (Sponsor)
Sources (2)
Financing record 241; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.