Colt Rotterdam Data Centre

Roosendaal, North Brabant, NetherlandsOperating
Evidence
Planned critical IT
15 MW
Updated
Oct 28, 2026

Colt Rotterdam is the operating Roosendaal facility. The 15 MW value is described as maximum potential and is therefore kept distinct from installed customer load, alongside more than 20 halls and 11,400 square metres of data-hall space. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Capacity

Reported capacity

Design

15 MW

Source

Reported capacity

Design

15 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

Colt Rotterdam is the operating Roosendaal facility. The 15 MW value is described as maximum potential and is therefore kept distinct from installed customer load, alongside more than 20 halls and 11,400 square metres of data-hall space. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.

Participants

Colt Data Centre Services

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Colt Rotterdam | Roosendaal | North Brabant | NL

Source

Location context

Actual

Colt Rotterdam | Roosendaal | North Brabant | NL

Source

Project location

Actual

Roosendaal, North Brabant, NL

Source

Data hall area

Actual

11,400 square metres

Source

Additional project facts

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

Colt Data Centre Services publishes 15 MW of IT power for this project boundary.

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

15 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Source

Operator confirmed

Actual

Colt Data Centre Services

Source

Current lifecycle

Actual

Operating

Source

Capacity classification

Actual

It load

Source

Capacity basis

Actual

15 MW is the operator published facility IT-load boundary; it is not measured customer utilization.

Source

Customer utilization

Actual

Not publicly disclosed

Source

Identity boundary

Actual

This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios

Source

Source refresh date

Actual

2026-08-29

Source

Data hall count

Actual

20 data halls

Source

Infrastructure & permits

Technical details (3)
Electric grid

Operational

15 MW

15 MW is the operator-published facility IT-load boundary; it is not measured customer utilization.

Fiber

Operational

Carrier-neutral or resilient fibre connectivity is described for the individual facility.

Cooling system

Operational

Cooling architecture supports the stated lifecycle; actual tenant draw and instantaneous load remain undisclosed.

Public-source research. Plans may change. See Evidence for sources and qualifications.