Cartis diligence evidence schedule

CleanCore West Texas AI Data Center Campus

PRJ-0699 · Site · Texas, United States

Record last updated Oct 28, 2026

Scope and capacity

CleanCore Solutions closed on the initial phase of a West Texas AI data-center site. The disclosed first phase covers 200 MW, with the site described as capable of scaling beyond 500 MW. CleanCore Solutions is associated with the development in West Texas location undisclosed, TX, US. The disclosed development scope includes 200 MW initial planned phase; more than 500 MW potential; precise location undisclosed. Power and physical infrastructure include phased West Texas campus development. CleanCore identifies 200 MW for the initial transaction phase. The sponsor committed to fund the initial 200 MW development through 2029, including $100 million expected by the first quarter of 2027.

Headline: 200 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · CleanCore AI campus | West Texas | precise boundary undisclosed

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 57936 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Lifecycle status · Preconstruction

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 57937 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Reported capacity · 200 MW

Planned / design or future potential · CleanCore West Texas AI Data Center Campus (Project)

Claim 57938 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Capacity basis · CleanCore identifies 200 MW for the initial transaction phase.

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 57939 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Location context · CleanCore AI campus | West Texas | precise boundary undisclosed

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 111363 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Lifecycle status · Preconstruction

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 111364 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Reported capacity · 200 MW

Planned / design or future potential · CleanCore West Texas AI Data Center Campus (Project)

Claim 111365 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Capacity basis · CleanCore identifies 200 MW for the initial transaction phase.

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 111366 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

Development scale · 200 MW initial planned phase

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 111383 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

  2. West Texas campus closing disclosure

    CleanCore Solutions · Document date: Jul 9, 2026 · Corroborating

    Source reference: SRC-6239 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea029747101ex99-1.htm

Development milestone · More than 500 MW potential

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 111384 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

  2. West Texas campus closing disclosure

    CleanCore Solutions · Document date: Jul 9, 2026 · Corroborating

    Source reference: SRC-6239 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea029747101ex99-1.htm

Power arrangement · Precise location undisclosed.

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 111385 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

  2. West Texas campus closing disclosure

    CleanCore Solutions · Document date: Jul 9, 2026 · Corroborating

    Source reference: SRC-6239 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea029747101ex99-1.htm

Site configuration · CleanCore AI campus | West Texas | precise boundary undisclosed

Actual · CleanCore West Texas AI Data Center Campus (Project)

Claim 111386 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. CleanCore closes initial West Texas data center transaction

    CleanCore Solutions · Document date: Jul 31, 2026 · Primary

    Source reference: SRC-3161 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea0297471-8k_cleancore.htm

  2. West Texas campus closing disclosure

    CleanCore Solutions · Document date: Jul 9, 2026 · Corroborating

    Source reference: SRC-6239 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1956741/000121390026076740/ea029747101ex99-1.htm

Counterparties and capital

CleanCore Solutions · Developer · CMP-1439

Equity investment

$100,000,000 · Jul 9, 2026

Near-term funding toward the initial 200 MW West Texas development.

CleanCore Solutions (Sponsor)

Financing record 214; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.