Cartis diligence evidence schedule

Cipher Black Pearl AI Data Center Campus

PRJ-0726 · Site · Wink, Texas, United States

Captured 2026-09-06T04:13:04.550Z · Record last updated 2026-08-27

SHA-256: 5e21929ebf62229408f68ae3b572cefb6cb759f6fc56993a0d8b071a7da8f9fd

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Cipher is converting Black Pearl into a contracted HPC campus. The first capacity was delivered to its tenant in August 2026 while remaining data halls continue through fit-out and construction. Cipher Digital and Amazon Web Services is publicly identified in the project record for Wink, Winkler County, TX, US. The disclosed development record includes 300 MW gross contracted campus capacity; first tenant capacity delivered in August 2026; remaining phases under construction. Power and infrastructure include grid-powered campus with air- and liquid-cooled data halls. Cipher identifies 300 MW of gross contracted HPC capacity at Black Pearl. Cipher reported a $2.0 billion high-yield bond financing supporting the contracted Black Pearl development.

Headline: 300 MW Contracted

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Location Context · Black Pearl campus | Wink | Winkler County | Texas

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 58751 · Review: Approved · Claim date: Not published

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm

Lifecycle Status · Partially operational

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 58752 · Review: Approved · Claim date: Not published

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm

Reported Capacity · 300 MW

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 58753 · Review: Approved · Claim date: Not published

Headline treatment: Selected headline

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm

Capacity Basis · Cipher identifies 300 MW of gross contracted HPC capacity at Black Pearl.

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 58754 · Review: Approved · Claim date: Not published

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm

Development Scale · 300 MW gross contracted campus capacity

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 107564 · Review: Approved · Claim date: Not published

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Q4 2025 business update

    Cipher Digital · Document date: 2026-02-01 · Corroborating

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000007/cipherdigital_businessup.htm

Development Milestone · First tenant capacity delivered in August 2026

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 107565 · Review: Approved · Claim date: Not published

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Q4 2025 business update

    Cipher Digital · Document date: 2026-02-01 · Corroborating

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000007/cipherdigital_businessup.htm

Power Arrangement · Remaining phases under construction.

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 107566 · Review: Approved · Claim date: Not published

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Q4 2025 business update

    Cipher Digital · Document date: 2026-02-01 · Corroborating

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000007/cipherdigital_businessup.htm

Boundary Context · Black Pearl campus | Wink | Winkler County | Texas

actual · Cipher Black Pearl AI Data Center Campus (project)

Claim 107567 · Review: Approved · Claim date: Not published

  1. Cipher Digital Q2 2026 business update

    Cipher Digital · Document date: 2026-08-10 · Primary

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000038/cipherdigital_businessup.htm
  2. Cipher Q4 2025 business update

    Cipher Digital · Document date: 2026-02-01 · Corroborating

    https://www.sec.gov/Archives/edgar/data/1819989/000181998926000007/cipherdigital_businessup.htm

Counterparties and capital

Amazon Web Services · Tenant · CMP-0152

Cipher Digital · Developer · CMP-1462

Debt Financing

$2,000,000,000 · 2026-02-01

Black Pearl construction through substantial completion.

Cipher Digital (Sponsor)

Financing record 206; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.