CalEthos Campus Site 1

Calipatria, California, United StatesOn hold / Delayed
Capacity
No public figure
Lead participant
CalEthos
Developer
Last updated
Aug 29, 2026
Most recent public record update

About CalEthos Campus Site 1

CalEthos proposed one 300 MW wholesale colocation campus on an 80-acre site in Imperial County, California; company filings do not support two independent 500 MW Calipatria sites. The company later disclosed that approval timing had slipped, and the record is retained as a held historical segment pending consolidation into the single campus identity.

Projects sharing a market, utility, or organization.

1 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

1 phases · 2 milestones
Historical proposal; identity consolidation requiredChanged Or Cancelled

CalEthos proposed one 300 MW wholesale colocation campus on an 80-acre site in Imperial County, California; company filings do not support two independent 500 MW Calipatria sites. The company later disclosed that approval timing had slipped, and the record is retained as a held historical segment pending consolidation into the single campus identity.

Dec 7, 2023
Company reported Phase I development complete
Completed
May 1, 2025
Company concluded approval timelines would not be met
Completed

Infrastructure

Renewable Energy SupplyPotential Or Planned

300 MW

Original clean-energy delivery concept for one campus.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

5 facts
Location Context
CalEthos Campus Site 1 | Calipatria | California | US
Actual
Lifecycle Status
Delayed
Actual
Site Area
80 acres
Actual
Campus Count
1 campus
Actual
Approval Status
Timelines not met by May 2025