Cartis diligence evidence schedule
Bitdeer Tydal AI Data Center
PRJ-0681 · Site · Tydal, Trøndelag, Norway
Record last updated Oct 28, 2026
Scope and capacity
Bitdeer is converting and expanding its Tydal campus in Norway under a 16-year AI/HPC colocation lease. The contracted program covers 121 MW of critical IT load supported by about 133 MW gross capacity, with another 47 MW gross reserved for later expansion. Bitdeer Technologies Group, Data Center Installations AS is associated with the development in Tydal, Tydal Municipality, Trøndelag, NO. The disclosed development scope includes 121 MW contracted critical IT; approximately 133 MW gross support capacity; 47 MW gross future expansion; first phase targeted by year-end 2026. Power and physical infrastructure include hydropower-backed campus using NVIDIA Vera Rubin reference architecture across four leased data halls. A 16-year colocation lease covers 121 MW of critical IT load. The 16-year lease has a stated base value of approximately $4.7 billion, with extension options described separately.
Headline: 121 MW Contracted
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · Tydal Data Center | Tydal | Trøndelag | Norway
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 57154 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Lifecycle status · Construction
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 57155 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Reported capacity · 180 MW
Planned / design or future potential · Bitdeer Tydal AI Data Center (Project)
Claim 57156 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Capacity basis · Bitdeer states 180 MW of gross installed capacity for the converted facility.
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 57157 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Location context · Tydal Data Center | Tydal | Trøndelag | Norway
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111207 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Lifecycle status · Construction
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111208 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Reported capacity · 121 MW
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111209 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Capacity basis · A 16-year colocation lease covers 121 MW of critical IT load.
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111210 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Development scale · 121 MW contracted critical IT
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111227 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Tydal AI/HPC lease announcement
Bitdeer Technologies Group · Document date: Aug 4, 2026 · Corroborating
Source reference: SRC-6207 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Development milestone · Approximately 133 MW gross support capacity
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111228 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Tydal AI/HPC lease announcement
Bitdeer Technologies Group · Document date: Aug 4, 2026 · Corroborating
Source reference: SRC-6207 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Power arrangement · 47 MW gross future expansion
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111229 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Tydal AI/HPC lease announcement
Bitdeer Technologies Group · Document date: Aug 4, 2026 · Corroborating
Source reference: SRC-6207 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Site configuration · First phase targeted by year end 2026.
Actual · Bitdeer Tydal AI Data Center (Project)
Claim 111230 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Tydal AI/HPC lease announcement
Bitdeer Technologies Group · Document date: Aug 4, 2026 · Corroborating
Source reference: SRC-6207 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
https://ir.bitdeer.com/news-releases/news-release-details/bitdeer-announces-47-billion-16-year-aihpc-data-center-lease
- Bitdeer engages DCI to finalize Tydal AI data center
Bitdeer Technologies Group · Document date: Mar 30, 2026 · Primary
Source reference: SRC-3113 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
https://www.globenewswire.com/news-release/2026/03/30/3264318/0/en/bitdeer-engages-dci-to-finalise-development-of-norway-s-largest-ai-data-center.html/
Counterparties and capital
Bitdeer Technologies Group · Developer · CMP-1423
Data Center Installations AS · Contractor · CMP-1424
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.