Cartis diligence evidence schedule

Bitdeer Clarington AI Data Center Campus

PRJ-0721 · Site · Clarington, Ohio, United States

Record last updated Oct 28, 2026

Scope and capacity

Bitdeer is preparing its Clarington, Ohio site for colocation development. The company reports 570 MW of power under contract, while timing remains exposed to permitting and ongoing legal proceedings. Bitdeer Technologies Group is publicly identified in the project record for Clarington, Monroe County area, OH, US. The disclosed development record includes 570 MW utility power under contract; design and preparation underway; construction timing not fixed. Power and infrastructure include large contracted-power site being prepared for colocation infrastructure. Bitdeer reports 570 MW of power under contract with a local utility.

Headline: 570 MW Contracted

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Bitdeer campus | Clarington | Ohio

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 58731 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

Lifecycle status · Preconstruction

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 58732 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

Reported capacity · 570 MW

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 58733 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

Capacity basis · Bitdeer reports 570 MW of power under contract with a local utility.

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 58734 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

Development scale · 570 MW utility power under contract

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 107524 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

  2. Bitdeer Clarington investor presentation

    Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating

    Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e

Development milestone · Design and preparation underway

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 107525 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

  2. Bitdeer Clarington investor presentation

    Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating

    Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e

Power arrangement · Construction timing not fixed.

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 107526 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

  2. Bitdeer Clarington investor presentation

    Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating

    Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e

Boundary context · Bitdeer campus | Clarington | Ohio

Actual · Bitdeer Clarington AI Data Center Campus (Project)

Claim 107527 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Bitdeer first-quarter 2026 results — infrastructure summary

    Bitdeer Technologies Group · Document date: May 12, 2026 · Primary

    Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm

  2. Bitdeer Clarington investor presentation

    Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating

    Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e

Counterparties and capital

Bitdeer Technologies Group · Developer · CMP-1423

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.