Cartis diligence evidence schedule
Bitdeer Clarington AI Data Center Campus
PRJ-0721 · Site · Clarington, Ohio, United States
Record last updated Oct 28, 2026
Scope and capacity
Bitdeer is preparing its Clarington, Ohio site for colocation development. The company reports 570 MW of power under contract, while timing remains exposed to permitting and ongoing legal proceedings. Bitdeer Technologies Group is publicly identified in the project record for Clarington, Monroe County area, OH, US. The disclosed development record includes 570 MW utility power under contract; design and preparation underway; construction timing not fixed. Power and infrastructure include large contracted-power site being prepared for colocation infrastructure. Bitdeer reports 570 MW of power under contract with a local utility.
Headline: 570 MW Contracted
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (8)
Location context · Bitdeer campus | Clarington | Ohio
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 58731 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
Lifecycle status · Preconstruction
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 58732 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
Reported capacity · 570 MW
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 58733 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
Capacity basis · Bitdeer reports 570 MW of power under contract with a local utility.
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 58734 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
Development scale · 570 MW utility power under contract
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 107524 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
- Bitdeer Clarington investor presentation
Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating
Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
Development milestone · Design and preparation underway
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 107525 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
- Bitdeer Clarington investor presentation
Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating
Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
Power arrangement · Construction timing not fixed.
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 107526 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
- Bitdeer Clarington investor presentation
Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating
Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
Boundary context · Bitdeer campus | Clarington | Ohio
Actual · Bitdeer Clarington AI Data Center Campus (Project)
Claim 107527 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bitdeer first-quarter 2026 results — infrastructure summary
Bitdeer Technologies Group · Document date: May 12, 2026 · Primary
Source reference: SRC-3211 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
https://www.sec.gov/Archives/edgar/data/1899123/000121390026044036/ea028584801ex99-1.htm
- Bitdeer Clarington investor presentation
Bitdeer Technologies Group · Document date: Feb 1, 2026 · Corroborating
Source reference: SRC-5992 · Fact sheet · Recorded authority: Official primary
Source URL
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
https://ir.bitdeer.com/static-files/0a37e4b4-b583-4274-9a82-15e62958019e
Counterparties and capital
Bitdeer Technologies Group · Developer · CMP-1423
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.