Bell AI Fabric TRU Data Centre
- Planned / design
- 26 MW
- Updated
- Oct 28, 2026
Bell AI Fabric TRU Data Centre is a physical data center on Thompson Rivers University Community Trust land at 1452 McGill Road. The original 2026 opening forecast is superseded by the Trust's late-2027 anticipated completion.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Anticipated completion moved from 2026 launch guidance to late 2027.
Milestones (2)
Apr 9, 2026 · Recorded actual event
Completed · Construction started
Source not linked2027 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- TRU Community Trust advances data centre development · Apr 9, 2026 · Primary
Other participants (1)
Supplier
Sources by role
Supplier (1)
- Bell Canada Increases Sovereign AI Capacity with Bell AI Fabric · May 28, 2025 · Primary
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (3)
Under construction
26 MW original design
Original Bell roadmap capacity; current utility and delivery instruments not published.
Planned or represented
Planned BCNET integration.
Planned or represented
Waste-heat integration described in Bell launch materials; implementation evidence pending.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.