Cartis diligence evidence schedule
AWS Warren County Data Center Campus
PRJ-0110 · Site · Vicksburg / Dana Road, Mississippi, United States
Record last updated Oct 28, 2026
Scope and capacity
AWS announced at least $3 billion for a new data-center campus in Warren County near Vicksburg. AWS Warren County Data Center Campus is in Vicksburg / Dana Road, MS, US and is a data center campus with preconstruction status.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (4)
Announced investment · $3 billions
Source report · AWS Warren County Data Center Campus (Project)
Claim 11867 · Recorded claim type: Not stated · Review: Approved · Claim date: Nov 20, 2025
- Amazon awards nearly $250,000 from Warren County Community Fund
Amazon · Document date: Aug 6, 2026 · Corroborating
Source reference: SRC-0739 · Company announcement · Recorded authority: Party primary
Source URL
https://press.aboutamazon.com/community/2026/8/amazon-awards-nearly-250-000-to-warren-county-community-fund-recipients
https://press.aboutamazon.com/community/2026/8/amazon-awards-nearly-250-000-to-warren-county-community-fund-recipients
- Amazon announces $25 billion statewide Mississippi expansion
Office of the Mississippi Governor · Document date: Apr 9, 2026 · Corroborating
Source reference: SRC-0737 · Government record · Recorded authority: Official primary
Source URL
https://governorreeves.ms.gov/amazon-continues-mississippi-expansion-announcing-plans-to-invest-a-total-of-25-billion-across-the-magnolia-state/
https://governorreeves.ms.gov/amazon-continues-mississippi-expansion-announcing-plans-to-invest-a-total-of-25-billion-across-the-magnolia-state/
- Amazon announces $3 billion Mississippi data-center investment
Amazon · Document date: Nov 20, 2025 · Primary
Source reference: SRC-0734 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment
https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment
- Amazon plans $3 billion Vicksburg investment
Office of the Mississippi Governor · Document date: Nov 20, 2025 · Corroborating
Source reference: SRC-0735 · Government record · Recorded authority: Official primary
Source URL
https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
- Amazon plans $3 billion in Vicksburg
Mississippi Development Authority · Document date: Nov 20, 2025 · Corroborating
Source reference: SRC-0736 · Government record · Recorded authority: Official primary
Source URL
https://mississippi.org/news/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
https://mississippi.org/news/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
- Amazon Warren County deal uses existing state framework
Mississippi Today · Document date: Nov 20, 2025 · Corroborating
Source reference: SRC-0741 · News report · Recorded authority: Secondary
Source URL
https://mississippitoday.org/2025/11/20/amazon-data-center-warren-county-mississippi/
https://mississippitoday.org/2025/11/20/amazon-data-center-warren-county-mississippi/
- Entergy Mississippi data-center service
Entergy · Document date: Not stated · Corroborating
Source reference: SRC-0738 · Company announcement · Recorded authority: Party primary
Source URL
https://www.entergy.com/datacenters/mississippi
https://www.entergy.com/datacenters/mississippi
Direct job target · 200 jobs
Source report · AWS Warren County Data Center Campus (Project)
Claim 11868 · Recorded claim type: Not stated · Review: Approved · Claim date: Nov 20, 2025
- Amazon announces $3 billion Mississippi data-center investment
Amazon · Document date: Nov 20, 2025 · Primary
Source reference: SRC-0734 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment
https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment
- Amazon plans $3 billion Vicksburg investment
Office of the Mississippi Governor · Document date: Nov 20, 2025 · Corroborating
Source reference: SRC-0735 · Government record · Recorded authority: Official primary
Source URL
https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
Additional regional job estimate · 300 jobs
Source report · AWS Warren County Data Center Campus (Project)
Claim 11869 · Recorded claim type: Not stated · Review: Approved · Claim date: Nov 20, 2025
- Amazon announces $3 billion Mississippi data-center investment
Amazon · Document date: Nov 20, 2025 · Primary
Source reference: SRC-0734 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment
https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment
- Amazon plans $3 billion Vicksburg investment
Office of the Mississippi Governor · Document date: Nov 20, 2025 · Corroborating
Source reference: SRC-0735 · Government record · Recorded authority: Official primary
Source URL
https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/
Community fund awards · $250,000
Reported rounded · AWS Warren County Data Center Campus (Project)
Claim 11872 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Aug 6, 2026
- Amazon awards nearly $250,000 from Warren County Community Fund
Amazon · Document date: Aug 6, 2026 · Primary
Source reference: SRC-0739 · Company announcement · Recorded authority: Party primary
Source URL
https://press.aboutamazon.com/community/2026/8/amazon-awards-nearly-250-000-to-warren-county-community-fund-recipients
https://press.aboutamazon.com/community/2026/8/amazon-awards-nearly-250-000-to-warren-county-community-fund-recipients
Counterparties and capital
Amazon Web Services · Developer · CMP-0152
Entergy Mississippi · Utility provider · CMP-0413
Mississippi Development Authority · Government authority · CMP-0374
Warren County, Mississippi · Government authority · CMP-0411
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.