AWS announced at least $3 billion for a new data-center campus in Warren County near Vicksburg. AWS Warren County Data Center Campus is in Vicksburg / Dana Road, MS, US and is a data center campus with preconstruction status.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Announced investment · $3 billions

Source report · AWS Warren County Data Center Campus (Project)

Claim 11867 · Recorded claim type: Not stated · Review: Approved · Claim date: Nov 20, 2025

  1. Amazon awards nearly $250,000 from Warren County Community Fund

    Amazon · Document date: Aug 6, 2026 · Corroborating

    Source reference: SRC-0739 · Company announcement · Recorded authority: Party primary

    Source URL

    https://press.aboutamazon.com/community/2026/8/amazon-awards-nearly-250-000-to-warren-county-community-fund-recipients

  2. Amazon announces $25 billion statewide Mississippi expansion

    Office of the Mississippi Governor · Document date: Apr 9, 2026 · Corroborating

    Source reference: SRC-0737 · Government record · Recorded authority: Official primary

    Source URL

    https://governorreeves.ms.gov/amazon-continues-mississippi-expansion-announcing-plans-to-invest-a-total-of-25-billion-across-the-magnolia-state/

  3. Amazon announces $3 billion Mississippi data-center investment

    Amazon · Document date: Nov 20, 2025 · Primary

    Source reference: SRC-0734 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment

  4. Amazon plans $3 billion Vicksburg investment

    Office of the Mississippi Governor · Document date: Nov 20, 2025 · Corroborating

    Source reference: SRC-0735 · Government record · Recorded authority: Official primary

    Source URL

    https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/

  5. Amazon plans $3 billion in Vicksburg

    Mississippi Development Authority · Document date: Nov 20, 2025 · Corroborating

    Source reference: SRC-0736 · Government record · Recorded authority: Official primary

    Source URL

    https://mississippi.org/news/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/

  6. Amazon Warren County deal uses existing state framework

    Mississippi Today · Document date: Nov 20, 2025 · Corroborating

    Source reference: SRC-0741 · News report · Recorded authority: Secondary

    Source URL

    https://mississippitoday.org/2025/11/20/amazon-data-center-warren-county-mississippi/

  7. Entergy Mississippi data-center service

    Entergy · Document date: Not stated · Corroborating

    Source reference: SRC-0738 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.entergy.com/datacenters/mississippi

Direct job target · 200 jobs

Source report · AWS Warren County Data Center Campus (Project)

Claim 11868 · Recorded claim type: Not stated · Review: Approved · Claim date: Nov 20, 2025

  1. Amazon announces $3 billion Mississippi data-center investment

    Amazon · Document date: Nov 20, 2025 · Primary

    Source reference: SRC-0734 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment

  2. Amazon plans $3 billion Vicksburg investment

    Office of the Mississippi Governor · Document date: Nov 20, 2025 · Corroborating

    Source reference: SRC-0735 · Government record · Recorded authority: Official primary

    Source URL

    https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/

Additional regional job estimate · 300 jobs

Source report · AWS Warren County Data Center Campus (Project)

Claim 11869 · Recorded claim type: Not stated · Review: Approved · Claim date: Nov 20, 2025

  1. Amazon announces $3 billion Mississippi data-center investment

    Amazon · Document date: Nov 20, 2025 · Primary

    Source reference: SRC-0734 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.aboutamazon.com/news/company-news/amazon-3-billion-mississippi-data-center-investment

  2. Amazon plans $3 billion Vicksburg investment

    Office of the Mississippi Governor · Document date: Nov 20, 2025 · Corroborating

    Source reference: SRC-0735 · Government record · Recorded authority: Official primary

    Source URL

    https://governorreeves.ms.gov/governor-tate-reeves-announces-amazon-plans-to-invest-3-billion-in-vicksburg/

Community fund awards · $250,000

Reported rounded · AWS Warren County Data Center Campus (Project)

Claim 11872 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Aug 6, 2026

  1. Amazon awards nearly $250,000 from Warren County Community Fund

    Amazon · Document date: Aug 6, 2026 · Primary

    Source reference: SRC-0739 · Company announcement · Recorded authority: Party primary

    Source URL

    https://press.aboutamazon.com/community/2026/8/amazon-awards-nearly-250-000-to-warren-county-community-fund-recipients

Counterparties and capital

Amazon Web Services · Developer · CMP-0152

Entergy Mississippi · Utility provider · CMP-0413

Mississippi Development Authority · Government authority · CMP-0374

Warren County, Mississippi · Government authority · CMP-0411