Cartis diligence evidence schedule
AWS Ridgeland Costa Site Campus
PRJ-0422 · Site · Ridgeland / County Line Road area, Mississippi, United States
Record last updated Oct 28, 2026
Scope and capacity
AWS's Ridgeland campus is a separate construction-stage site in southern Madison County. AWS Ridgeland Costa Site Campus is located in Ridgeland / County Line Road area, MS, US and is a data center campus in construction status.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (10)
Current status · Construction
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39679 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Where do Amazon's data centers in Mississippi stand?
Mississippi Today · Document date: Jun 9, 2026 · Primary
Source reference: SRC-2227 · Recorded authority: Secondary
Source URL
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
- Construction industry steps up for Mississippi AWS project
Mississippi Monitor · Document date: Sep 10, 2024 · Corroborating
Source reference: SRC-2238 · Recorded authority: Secondary
Source URL
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
Operation verified · False
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39680 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Where do Amazon's data centers in Mississippi stand?
Mississippi Today · Document date: Jun 9, 2026 · Primary
Source reference: SRC-2227 · Recorded authority: Secondary
Source URL
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
Site area reported · 786 acres
Reported rounded · AWS Ridgeland Costa Site Campus (Project)
Claim 39681 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Construction industry steps up for Mississippi AWS project
Mississippi Monitor · Document date: Sep 10, 2024 · Primary
Source reference: SRC-2238 · Recorded authority: Secondary
Source URL
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
Site name · Costa Site
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39682 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Amazon Data Center Overview - Madison County, Mississippi
City of Ridgeland and Madison County partners · Document date: Jun 1, 2026 · Corroborating
Source reference: SRC-2234 · Recorded authority: Official primary
Source URL
https://www.ridgelandms.org/wp-content/uploads/2026/06/Madison-County-MS-Brochure_DIGITAL-VERSION.pdf
https://www.ridgelandms.org/wp-content/uploads/2026/06/Madison-County-MS-Brochure_DIGITAL-VERSION.pdf
- Construction industry steps up for Mississippi AWS project
Mississippi Monitor · Document date: Sep 10, 2024 · Primary
Source reference: SRC-2238 · Recorded authority: Secondary
Source URL
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
Permit code · JAN200
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39683 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Construction industry steps up for Mississippi AWS project
Mississippi Monitor · Document date: Sep 10, 2024 · Primary
Source reference: SRC-2238 · Recorded authority: Secondary
Source URL
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
Building pad work reported · True
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39684 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Construction industry steps up for Mississippi AWS project
Mississippi Monitor · Document date: Sep 10, 2024 · Primary
Source reference: SRC-2238 · Recorded authority: Secondary
Source URL
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
Completed building count disclosed · False
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39685 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Where do Amazon's data centers in Mississippi stand?
Mississippi Today · Document date: Jun 9, 2026 · Corroborating
Source reference: SRC-2227 · Recorded authority: Secondary
Source URL
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
- Construction industry steps up for Mississippi AWS project
Mississippi Monitor · Document date: Sep 10, 2024 · Primary
Source reference: SRC-2238 · Recorded authority: Secondary
Source URL
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
https://www.themississippimonitor.com/construction-industry-steps-up-for-mississippis-grandest-project-aws/
Campus IT capacity disclosed · False
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39686 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Where do Amazon's data centers in Mississippi stand?
Mississippi Today · Document date: Jun 9, 2026 · Corroborating
Source reference: SRC-2227 · Recorded authority: Secondary
Source URL
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
https://mississippitoday.org/2026/06/09/amazon-data-centers-mississippi/
- Amazon to invest USD25 billion in Mississippi data centers
Amazon · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2224 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aboutamazon.com/news/company-news/amazon-25-billion-mississippi-data-centers
https://www.aboutamazon.com/news/company-news/amazon-25-billion-mississippi-data-centers
Site investment disclosed · False
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39687 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Amazon continues Mississippi expansion
Madison County Economic Development Authority · Document date: Apr 9, 2026 · Primary
Source reference: SRC-2225 · Government record · Recorded authority: Official primary
Source URL
https://madisoncountyeda.com/amazon-continues-mississippi-expansion-announcing-plans-to-invest-a-total-of-25-billion-across-the-magnolia-state/
https://madisoncountyeda.com/amazon-continues-mississippi-expansion-announcing-plans-to-invest-a-total-of-25-billion-across-the-magnolia-state/
Program parent · AWS Mississippi Madison-Hinds Program
Actual · AWS Ridgeland Costa Site Campus (Project)
Claim 39688 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Amazon continues Mississippi expansion
Madison County Economic Development Authority · Document date: Apr 9, 2026 · Corroborating
Source reference: SRC-2225 · Government record · Recorded authority: Official primary
Source URL
https://madisoncountyeda.com/amazon-continues-mississippi-expansion-announcing-plans-to-invest-a-total-of-25-billion-across-the-magnolia-state/
https://madisoncountyeda.com/amazon-continues-mississippi-expansion-announcing-plans-to-invest-a-total-of-25-billion-across-the-magnolia-state/
- AWS plans to invest USD10 billion in Mississippi
Amazon · Document date: Jan 25, 2024 · Primary
Source reference: SRC-2221 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aboutamazon.com/news/aws/aws-10-billion-investment-mississippi
https://www.aboutamazon.com/news/aws/aws-10-billion-investment-mississippi
Counterparties and capital
Amazon Web Services · Operator · CMP-0152
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.