Cartis diligence evidence schedule

AWS Project Green Montgomery County Campus

PRJ-0108 · Site · New Florence / High Hill, Missouri, United States

Record last updated Oct 28, 2026

Scope and capacity

AWS plans a $10-billion data-center campus in Montgomery County, Missouri, under the local codename Project Green. AWS Project Green Montgomery County Campus is in New Florence / High Hill, MO, US and is a data center campus with preconstruction status.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Announced investment · $10 billions

Actual · AWS Project Green Montgomery County Campus (Project)

Claim 11847 · Recorded claim type: Actual · Review: Approved · Claim date: Jun 15, 2026

  1. Montgomery County testimony on Project Green

    Missouri Public Service Commission · Document date: Jul 24, 2026 · Corroborating

    Source reference: SRC-0719 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://efis.psc.mo.gov/Document/Display/884092

  2. Amazon commits $10 billion to Montgomery County campus

    Data Center Dynamics · Document date: Jun 16, 2026 · Corroborating

    Source reference: SRC-0724 · News report · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/amazon-commits-10bn-to-data-center-campus-in-montgomery-city-missouri/

  3. Amazon announces data-center investment in Montgomery County

    Amazon · Document date: Jun 15, 2026 · Corroborating

    Source reference: SRC-0716 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.aboutamazon.com/news/company-news/amazon-data-center-missouri-new-jobs

  4. Amazon investing $10 billion in Montgomery County

    Office of the Missouri Governor · Document date: Jun 15, 2026 · Primary

    Source reference: SRC-0717 · Government record · Recorded authority: Official primary

    Source URL

    https://governor.mo.gov/press-releases/archive/amazon-investing-10-billion-montgomery-county

  5. New Florence AWS campus to use local aquifer

    KQ2 · Document date: Jun 3, 2026 · Corroborating

    Source reference: SRC-0723 · News report · Recorded authority: Secondary

    Source URL

    https://www.kq2.com/news/regional/missouri/2026/06/03/new-florence-aws-data-center-to-tap-local-aquifer-for-water/

  6. Project Green plan and cost-benefit analysis

    Montgomery County, Missouri · Document date: Feb 1, 2026 · Corroborating

    Source reference: SRC-0721 · Government record · Recorded authority: Official primary

    Source URL

    https://mcmo.us/wp-content/uploads/2026/02/Plan-Cost-Benefit-Analysis-Project-Green.pdf

  7. Residents question proposed Amazon campus

    ABC 17 News · Document date: Dec 4, 2025 · Corroborating

    Source reference: SRC-0722 · News report · Recorded authority: Secondary

    Source URL

    https://abc17news.com/news/montgomery/2025/12/04/montgomery-county-residents-push-back-against-amazon-data-center/

  8. Amazon data center: Ameren customer protections

    Ameren Missouri · Document date: Not stated · Corroborating

    Source reference: SRC-0718 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.ameren.com/resource-center/amazon

Public job target · 400 jobs

Source report · AWS Project Green Montgomery County Campus (Project)

Claim 11848 · Recorded claim type: Not stated · Review: Approved · Claim date: Jun 15, 2026

  1. Amazon announces data-center investment in Montgomery County

    Amazon · Document date: Jun 15, 2026 · Primary

    Source reference: SRC-0716 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.aboutamazon.com/news/company-news/amazon-data-center-missouri-new-jobs

  2. Amazon investing $10 billion in Montgomery County

    Office of the Missouri Governor · Document date: Jun 15, 2026 · Corroborating

    Source reference: SRC-0717 · Government record · Recorded authority: Official primary

    Source URL

    https://governor.mo.gov/press-releases/archive/amazon-investing-10-billion-montgomery-county

Binding employment covenant · 150 jobs

Source report · AWS Project Green Montgomery County Campus (Project)

Claim 11849 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 24, 2026

  1. Montgomery County testimony on Project Green

    Missouri Public Service Commission · Document date: Jul 24, 2026 · Primary

    Source reference: SRC-0719 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://efis.psc.mo.gov/Document/Display/884092

Minimum building count · 4 buildings

Actual · Minimum buildout (Phase)

Claim 11851 · Recorded claim type: Actual · Review: Approved · Claim date: Dec 4, 2025

  1. Project Green plan and cost-benefit analysis

    Montgomery County, Missouri · Document date: Feb 1, 2026 · Primary

    Source reference: SRC-0721 · Government record · Recorded authority: Official primary

    Source URL

    https://mcmo.us/wp-content/uploads/2026/02/Plan-Cost-Benefit-Analysis-Project-Green.pdf

  2. Residents question proposed Amazon campus

    ABC 17 News · Document date: Dec 4, 2025 · Corroborating

    Source reference: SRC-0722 · News report · Recorded authority: Secondary

    Source URL

    https://abc17news.com/news/montgomery/2025/12/04/montgomery-county-residents-push-back-against-amazon-data-center/

Maximum building count · 17 buildings

Actual · Maximum local buildout (Phase)

Claim 11852 · Recorded claim type: Actual · Review: Approved · Claim date: Dec 4, 2025

  1. Project Green plan and cost-benefit analysis

    Montgomery County, Missouri · Document date: Feb 1, 2026 · Primary

    Source reference: SRC-0721 · Government record · Recorded authority: Official primary

    Source URL

    https://mcmo.us/wp-content/uploads/2026/02/Plan-Cost-Benefit-Analysis-Project-Green.pdf

  2. Residents question proposed Amazon campus

    ABC 17 News · Document date: Dec 4, 2025 · Corroborating

    Source reference: SRC-0722 · News report · Recorded authority: Secondary

    Source URL

    https://abc17news.com/news/montgomery/2025/12/04/montgomery-county-residents-push-back-against-amazon-data-center/

Projected local revenue minimum · $400 millions over 25 years

Source report · AWS Project Green Montgomery County Campus (Project)

Claim 11854 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 24, 2026

  1. Montgomery County testimony on Project Green

    Missouri Public Service Commission · Document date: Jul 24, 2026 · Primary

    Source reference: SRC-0719 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://efis.psc.mo.gov/Document/Display/884092

Projected local revenue maximum · $1.80 billions over 25 years

Source report · AWS Project Green Montgomery County Campus (Project)

Claim 11855 · Recorded claim type: Not stated · Review: Approved · Claim date: Jul 24, 2026

  1. Montgomery County testimony on Project Green

    Missouri Public Service Commission · Document date: Jul 24, 2026 · Primary

    Source reference: SRC-0719 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://efis.psc.mo.gov/Document/Display/884092

Counterparties and capital

Amazon Web Services · Developer · CMP-0152

Ameren Missouri · Utility provider · CMP-0405

Missouri Public Service Commission · Government authority · CMP-0406

Montgomery County, Missouri · Government authority · CMP-0404

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.