AVAIO Digital Hercules Campus

PRJ-0613 · Site · Appomattox, Virginia, United States

Record last updated Oct 28, 2026

Scope and capacity

AVAIO Digital is developing the Hercules campus in Appomattox County, Virginia as an approximately $3 billion project. The power design combines about 300 MW of grid service with as much as 700 MW of behind-the-meter generation for a 1 GW baseload envelope. That figure describes the site power design, not IT capacity.

Headline: 1,000 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Hercules campus | Appomattox | Virginia | United States

Actual · AVAIO Digital Hercules Campus (Project)

Claim 54761 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Lifecycle status · Preconstruction

Actual · AVAIO Digital Hercules Campus (Project)

Claim 54762 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Reported capacity · 1,000 MW

Design · AVAIO Digital Hercules Campus (Project)

Claim 54763 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Capacity basis · Source stated total baseload power design, not critical IT load

Actual · AVAIO Digital Hercules Campus (Project)

Claim 54764 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Project identity · AVAIO Digital Hercules Campus

Actual · AVAIO Digital Hercules Campus (Project)

Claim 119663 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Lifecycle status · Development program

Actual · AVAIO Digital Hercules Campus (Project)

Claim 119664 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Location · Appomattox, Appomattox County, VA, US

Actual · AVAIO Digital Hercules Campus (Project)

Claim 119665 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Participant roles · AVAIO Digital

Actual · AVAIO Digital Hercules Campus (Project)

Claim 119666 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Capacity · 1,000 MW

Design · AVAIO Digital Hercules Campus (Project)

Claim 119667 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Capacity basis · 1,000 MW combined grid and behind the meter power design

Actual · AVAIO Digital Hercules Campus (Project)

Claim 119668 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Development scale · AVAIO Digital is developing the Hercules campus in Appomattox County, Virginia as an approximately $3 billion project. The power design combines about 300 MW of grid service with as much as 700 MW of behind the meter generation for a 1 GW baseload envelope

Actual · AVAIO Digital Hercules Campus (Project)

Claim 119669 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Infrastructure · That figure describes the site power design, not IT capacity.

Actual · AVAIO Digital Hercules Campus (Project)

Claim 119670 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AVAIO Digital Hercules project announcement

    Appomattox County, Virginia · Document date: Dec 10, 2024 · Corroborating

    Source reference: SRC-6549 · Government record · Recorded authority: Official primary

    Source URL

    https://www.appomattoxcountyva.gov/DocumentCenter/View/622/AVAIO_Appomattox-Press-Release-FINAL-12102024

  2. Hercules — Appomattox, Virginia

    AVAIO Digital · Document date: Not stated · Primary

    Source reference: SRC-2958 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.avaiodigital.com/developments/appomattox-virginia

Counterparties and capital

AVAIO Digital · Developer · CMP-1383

Investment commitment

$3,000,000,000 · Dec 10, 2024

Announced Hercules campus investment.

AVAIO Digital (Sponsor)

Financing record 246; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.