Cartis diligence evidence schedule
atNorth Haugaland NOR01 Mega Site
PRJ-0404 · Site · Haugaland Business Park, Tysvaer, Rogaland, Norway
Record last updated Oct 28, 2026
Scope and capacity
atNorth plans NOR01 on 36 hectares in Haugaland Business Park, with 120 MW initial phases, a path to 350 MW and power projected for 2028. atNorth Haugaland NOR01 Mega Site is located in Haugaland Business Park, Tysvaer, Rogaland, NO and is a data center campus in preconstruction status.
Headline: 350 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (15)
Land acquired or sale agreed · True
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37545 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
- Data center worth NOK11 billion planned in Haugaland Business Park
Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating
Source reference: SRC-2107 · Recorded authority: Party primary
Source URL
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
Site area · 36 hectares
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37546 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
- Data center worth NOK11 billion planned in Haugaland Business Park
Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating
Source reference: SRC-2107 · Recorded authority: Party primary
Source URL
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
- Haugaland NOR01 mega site
atNorth · Document date: Not stated · Corroborating
Source reference: SRC-2106 · Recorded authority: Party primary
Source URL
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
Site within haugaland business park · True
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37547 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
- Data center worth NOK11 billion planned in Haugaland Business Park
Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating
Source reference: SRC-2107 · Recorded authority: Party primary
Source URL
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
Initial planned site power · 120 MW
Planned / design or future potential · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37548 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
- Data center worth NOK11 billion planned in Haugaland Business Park
Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating
Source reference: SRC-2107 · Recorded authority: Party primary
Source URL
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
Future planned site power · 350 MW
Planned / design or future potential · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37549 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
- Haugaland NOR01 mega site
atNorth · Document date: Not stated · Corroborating
Source reference: SRC-2106 · Recorded authority: Party primary
Source URL
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
Projected power availability year · 2028
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37550 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
Statnett substation planned · True
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37552 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
Fagne substation planned · True
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37553 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
Zoning work started · True
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37554 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Data center worth NOK11 billion planned in Haugaland Business Park
Haugaland Naeringspark · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2107 · Recorded authority: Party primary
Source URL
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
Phase one investment estimate · 11 NOK billion
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37557 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth plans 350 MW Haugaland campus
Data Center Dynamics · Document date: Jun 4, 2026 · Corroborating
Source reference: SRC-2108 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/atnorth-plans-350mw-data-center-campus-in-norway/
https://www.datacenterdynamics.com/en/news/atnorth-plans-350mw-data-center-campus-in-norway/
- Data center worth NOK11 billion planned in Haugaland Business Park
Haugaland Naeringspark · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2107 · Recorded authority: Party primary
Source URL
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
Phase one operational jobs expected over · 70 jobs
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37558 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Data center worth NOK11 billion planned in Haugaland Business Park
Haugaland Naeringspark · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2107 · Recorded authority: Party primary
Source URL
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/
Full capacity on site jobs expected around · 200 jobs
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37559 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- atNorth expands to Norway with NOR01
atNorth · Document date: Jun 3, 2026 · Primary
Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary
Source URL
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/
Renewable power claim · 100 percent
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37560 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Haugaland NOR01 mega site
atNorth · Document date: Not stated · Primary
Source reference: SRC-2106 · Recorded authority: Party primary
Source URL
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
Design PUE at or below · 1.2 PUE
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37561 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Haugaland NOR01 mega site
atNorth · Document date: Not stated · Primary
Source reference: SRC-2106 · Recorded authority: Party primary
Source URL
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
Direct liquid cooling ready · True
Actual · atNorth Haugaland NOR01 Mega Site (Project)
Claim 37562 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Haugaland NOR01 mega site
atNorth · Document date: Not stated · Primary
Source reference: SRC-2106 · Recorded authority: Party primary
Source URL
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/
Counterparties and capital
atNorth · Developer, Operator · CMP-0965
Fagne · Utility provider · CMP-1000
Haugaland Naeringspark · Landowner · CMP-0997
Statnett · Utility provider · CMP-0999
Tysvaer Municipality · Government authority · CMP-0998
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.