Cartis diligence evidence schedule

atNorth Haugaland NOR01 Mega Site

PRJ-0404 · Site · Haugaland Business Park, Tysvaer, Rogaland, Norway

Record last updated Oct 28, 2026

Scope and capacity

atNorth plans NOR01 on 36 hectares in Haugaland Business Park, with 120 MW initial phases, a path to 350 MW and power projected for 2028. atNorth Haugaland NOR01 Mega Site is located in Haugaland Business Park, Tysvaer, Rogaland, NO and is a data center campus in preconstruction status.

Headline: 350 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Land acquired or sale agreed · True

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37545 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

  2. Data center worth NOK11 billion planned in Haugaland Business Park

    Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating

    Source reference: SRC-2107 · Recorded authority: Party primary

    Source URL

    https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/

Site area · 36 hectares

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37546 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

  2. Data center worth NOK11 billion planned in Haugaland Business Park

    Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating

    Source reference: SRC-2107 · Recorded authority: Party primary

    Source URL

    https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/

  3. Haugaland NOR01 mega site

    atNorth · Document date: Not stated · Corroborating

    Source reference: SRC-2106 · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/

Site within haugaland business park · True

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37547 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

  2. Data center worth NOK11 billion planned in Haugaland Business Park

    Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating

    Source reference: SRC-2107 · Recorded authority: Party primary

    Source URL

    https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/

Initial planned site power · 120 MW

Planned / design or future potential · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37548 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

  2. Data center worth NOK11 billion planned in Haugaland Business Park

    Haugaland Naeringspark · Document date: Jun 3, 2026 · Corroborating

    Source reference: SRC-2107 · Recorded authority: Party primary

    Source URL

    https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/

Future planned site power · 350 MW

Planned / design or future potential · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37549 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

  2. Haugaland NOR01 mega site

    atNorth · Document date: Not stated · Corroborating

    Source reference: SRC-2106 · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/

Projected power availability year · 2028

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37550 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

Statnett substation planned · True

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37552 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

Fagne substation planned · True

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37553 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

Zoning work started · True

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37554 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Data center worth NOK11 billion planned in Haugaland Business Park

    Haugaland Naeringspark · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2107 · Recorded authority: Party primary

    Source URL

    https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/

Phase one investment estimate · 11 NOK billion

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37557 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth plans 350 MW Haugaland campus

    Data Center Dynamics · Document date: Jun 4, 2026 · Corroborating

    Source reference: SRC-2108 · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/atnorth-plans-350mw-data-center-campus-in-norway/

  2. Data center worth NOK11 billion planned in Haugaland Business Park

    Haugaland Naeringspark · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2107 · Recorded authority: Party primary

    Source URL

    https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/

Phase one operational jobs expected over · 70 jobs

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37558 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Data center worth NOK11 billion planned in Haugaland Business Park

    Haugaland Naeringspark · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2107 · Recorded authority: Party primary

    Source URL

    https://haugaland-park.no/en/2026/06/03/datasenter-til-11-milliarder-planlagt-i-haugaland-naeringspark/

Full capacity on site jobs expected around · 200 jobs

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37559 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. atNorth expands to Norway with NOR01

    atNorth · Document date: Jun 3, 2026 · Primary

    Source reference: SRC-2105 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/news/atnorth-expands-to-norway-with-new-mega-site-in-haugaland/

Renewable power claim · 100 percent

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37560 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haugaland NOR01 mega site

    atNorth · Document date: Not stated · Primary

    Source reference: SRC-2106 · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/

Design PUE at or below · 1.2 PUE

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37561 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haugaland NOR01 mega site

    atNorth · Document date: Not stated · Primary

    Source reference: SRC-2106 · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/

Direct liquid cooling ready · True

Actual · atNorth Haugaland NOR01 Mega Site (Project)

Claim 37562 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Haugaland NOR01 mega site

    atNorth · Document date: Not stated · Primary

    Source reference: SRC-2106 · Recorded authority: Party primary

    Source URL

    https://www.atnorth.com/nordic-data-centers/norway-data-centers/haugaland-nor01/

Counterparties and capital

atNorth · Developer, Operator · CMP-0965

Fagne · Utility provider · CMP-1000

Haugaland Naeringspark · Landowner · CMP-0997

Statnett · Utility provider · CMP-0999

Tysvaer Municipality · Government authority · CMP-0998

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.