atNorth Haugaland NOR01 Mega Site

Haugaland Business Park, Tysvaer, Rogaland, NorwayPreconstruction
Evidence
Planned / design
350 MW
Updated
Oct 28, 2026
Utility
Fagne · Statnett

atNorth plans NOR01 on 36 hectares in Haugaland Business Park, with 120 MW initial phases, a path to 350 MW and power projected for 2028. atNorth Haugaland NOR01 Mega Site is located in Haugaland Business Park, Tysvaer, Rogaland, NO and is a data center campus in preconstruction status.

Capacity

Initial planned site power

Planned / design or future potential

120 MW

Source

Future planned site power

Planned / design or future potential

350 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Initial NOR01 phasesAnnounced or preconstruction

Planned site-power capacity, not operating IT load.

NOR01 full rampAnnounced or preconstruction

Future design envelope dependent on power, zoning, demand and construction.

Milestones (3)
Haugaland Business Park announces NOR01 land sale

Jun 3, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
Zoning process begins for data center use

Jun 3, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
NOR01 initial power availability projected

2028 · Event timing type not established

Status not stated · Event type not stated

Source not linked

Participants

atNorth

Developer · Operator

Sources by role
Developer / Operator (1)
Developer (1)
Haugaland Naeringspark

Landowner

Sources by role
Other participants (3)
Fagne

Utility provider

Sources by role
Utility provider (1)
Utility provider (1)
Statnett

Utility provider

Sources by role
Utility provider (1)
Tysvaer Municipality

Government authority

Sources by role
Government authority (1)

Capital & incentives

Capital claims

Phase one investment estimate

Actual

11 NOK billion

Source

Site & development

Land acquired or sale agreed

Actual

True

Source

Site area

Actual

36 hectares

Source

Site within haugaland business park

Actual

True

Source

Full capacity on site jobs expected around

Actual

200 jobs

Source

Technical specifications

Projected power availability year

Actual

2028

Source

Renewable power claim

Actual

100 percent

Source

Direct liquid cooling ready

Actual

True

Source

Additional project facts

Statnett substation planned

Actual

True

Source

Fagne substation planned

Actual

True

Source

Zoning work started

Actual

True

Source

Phase one operational jobs expected over

Actual

70 jobs

Source

Design PUE at or below

Actual

1.2 PUE

Source

Infrastructure & permits

Technical details (4)
Utility service

Secured or contracted

120 MW

Facility contribution agreement for initial network capacity; service is projected for 2028.

Electric grid

Planned or represented

One of two substations required for planned power delivery.

Electric grid

Planned or represented

Regional-grid substation supporting NOR01; final schedule and energization evidence remain open.

Heat reuse

Potential or planned

Excess heat is to be made available, but no offtake agreement or delivery infrastructure is disclosed.

Permit · Under review

NOR01 Haugaland

Tysvaer Municipality

Jun 3, 2026

Sources (1)

Public-source research. Plans may change. See Evidence for sources and qualifications.