AtlasEdge LIS002 Lisbon Data Center

Lisbon, Lisbon District, PortugalPreconstruction
Evidence
Planned critical IT
16 MW
Updated
Oct 28, 2026

AtlasEdge LIS002 Lisbon Data Center is part of AtlasEdge’s three-phase Lisbon campus near the Carcavelos cable-landing corridor. The current facility capacity is kept separate from the 30 MW campus program. A €253 million sustainability-linked facility funds LIS001 and LIS002, with project-specific tranches recorded rather than attributed as standalone facility value. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Capacity

Reported capacity

Design

16 MW

Source

Reported capacity

Planned / design or future potential

16 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development, permitting and phased deliveryUnder construction

AtlasEdge LIS002 Lisbon Data Center is part of AtlasEdge’s three-phase Lisbon campus near the Carcavelos cable-landing corridor. The current facility capacity is kept separate from the 30 MW campus program. A €253 million sustainability-linked facility funds LIS001 and LIS002, with project-specific tranches recorded rather than attributed as standalone facility value. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Milestones (1)
AtlasEdge closed Lisbon campus green financing

Oct 28, 2025 · Recorded actual event

Completed · Financing

Source not linked

Participants

AtlasEdge

Developer

Sources by role
Developer (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Campus green financing

Closed financing

€253,000,000

Source

Financing records

Debt financing

€253,000,000

Oct 28, 2025

Shared LIS001/LIS002 campus financing; Facility A €63m and Facility B €190m.

Parties & sources

AtlasEdge (Borrower)

Site & development

Location context

Actual

LIS002 | Lisbon | Lisbon District | PT

Source

Location context

Actual

LIS002 | Lisbon | Lisbon District | PT

Source

Technical specifications

Renewable energy claim

Actual

100 percent

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

AtlasEdge publishes 16 MW for planned LIS002.

Source

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

16 MW is a published future facility or full build IT boundary; it is not operating load.

Source

Operator confirmed

Actual

AtlasEdge

Source

Facility capacity basis

Actual

16 MW is a published future facility or full build IT boundary; it is not operating load.

Source

Current lifecycle

Actual

Under development

Source

Operating model

Actual

Carrier neutral colocation

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

16 MW

Published IT design boundary; utility service and operating load remain distinct.

Fiber

Planned or represented

Carrier-neutral or resilient fibre connectivity described for the individual facility.

Public-source research. Plans may change. See Evidence for sources and qualifications.