Scope and capacity
HAM002 is an operating Ahrensburg facility with continuing expansion. Independent reporting identifies four phases, a 3.2 MW next tranche and 20 MW total power at full completion; 2 MW only as the earlier IT boundary and does not recast 20 MW as operating IT. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.
Headline: 11.2 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (13)
Location context · HAM002 | Hamburg | Hamburg | DE
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 68087 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Lifecycle status · Operating
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 68088 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Reported capacity · 11.2 MW
Design · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 68089 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Capacity basis · AtlasEdge publishes 11.2 MW of IT capacity at final expansion.
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 68090 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Location context · HAM002 | Hamburg | Hamburg | DE
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81051 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Lifecycle status · Operating
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81052 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Reported capacity · 11.2 MW
Design · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81053 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Capacity basis · 11.2 MW is the earlier published IT boundary; the current 20 MW expansion figure is total power and is separately classified as future utility capacity.
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81054 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Operator confirmed · AtlasEdge
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81055 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Facility capacity basis · 11.2 MW is the earlier published IT boundary; the current 20 MW expansion figure is total power and is separately classified as future utility capacity.
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81056 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Current lifecycle · Operating
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81057 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Operating model · Carrier neutral colocation
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81059 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Renewable energy claim · 100 percent
Actual · AtlasEdge HAM002 Hamburg Data Center (Project)
Claim 81060 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AtlasEdge HAM002 Hamburg Data Center official profile
AtlasEdge · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3888 · Fact sheet · Recorded authority: Official primary
Source URL
https://atlasedge.com/data-centres/hamburg/
https://atlasedge.com/data-centres/hamburg/
Counterparties and capital
AtlasEdge · Developer · CMP-1487
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.