Applied Digital Garden City Data Center
Garden City, Texas, United StatesOperating / Stabilized
Capacity
200 MW
Operating critical IT
Lead participant
Applied Digital Corporation
Developer
Last updated
Sep 1, 2026
Most recent public record update
About Applied Digital Garden City Data Center
Applied Digital developed and energized a 200 MW hosting facility near Garden City, Texas, on a long-term ground lease. The site was built beside wind generation and reached full energization in October 2023 for blockchain-compute hosting. Applied Digital later reported the sale of the Garden City location, so the operating site is presented separately from the company’s current North Dakota AI-campus strategy.
Capacity
Operating critical ITOperating capacity—An operating IT-capacity figure has not been publicly disclosed.
Design200 MWActual · Applied Digital Garden City Data Center
It Load200 MWActual · Applied Digital Garden City Data Center
Development
1 phases · 2 milestones200 MW hosting facilityOperational
Full 200 MW facility energized for hosting operations.
Oct 20, 2023
Full 200 MW facility energized
CompletedFeb 12, 2026
Applied Digital disclosed that the Garden City location had been sold
CompletedInfrastructure
Electric GridOperational
200 MW
Facility electrical design and energized hosting capacity.
Renewable Energy SupplyOperational
Site developed beside wind generation; the wind asset is not assigned as facility IT capacity.
Project map
0 of 1 project point mappedInfrastructure facts
2
Mapped records
1
Capacity figures
1
No map point available
Power & interconnection: 2
Facts & sources
Published claims and their source links.
Reported Capacity200 MW operating facility design capacity MWActual
200 MW operating facility design capacity MW
Ground Lease Term99 yearsActual
99 years