Cartis diligence evidence schedule

AirTrunk SYD2 Sydney North Data Center Campus

PRJ-0759 · Site · Sydney, New South Wales, Australia

Record last updated Oct 28, 2026

Scope and capacity

AirTrunk’s current SYD2 page identifies adjacent Apollo Place as Phase 5, with development ongoing in 2026, and records Shell C under construction in April 2026. The planned integrated campus expansion does not establish a new opening or justify adding an unqualified capacity figure to the existing campus total. AirTrunk's SYD2 campus operates in northern Sydney and has undergone a major expansion. The announced program lifts total capacity above 120 MW. AirTrunk is publicly identified in the project record for Sydney, Sydney North, NSW, AU. The disclosed development record includes more than 120 MW total campus capacity after expansion; earlier announced 70 MW expansion program; dedicated 200 MVA substation. Power and infrastructure include operational northern Sydney campus supported by a dedicated 132 kV substation. AirTrunk states the SYD2 expansion lifts total campus capacity above 120 MW.

Headline: 120 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · SYD2 campus | Sydney North | New South Wales

Actual · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 59558 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Lifecycle status · Partially operational

Actual · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 59559 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Reported capacity · 120 MW

Design · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 59560 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Capacity basis · AirTrunk states the SYD2 expansion lifts total campus capacity above 120 MW.

Actual · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 59561 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Development scale · More than 120 MW total campus capacity after expansion

Actual · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 107836 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AirTrunk Australia portfolio

    AirTrunk · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6071 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/location/australia/

  2. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Development milestone · 70 MW final phase expansion

Actual · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 107837 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AirTrunk Australia portfolio

    AirTrunk · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6071 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/location/australia/

  2. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Power arrangement · Dedicated 200 MVA substation.

Actual · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 107838 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AirTrunk Australia portfolio

    AirTrunk · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6071 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/location/australia/

  2. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Boundary context · SYD2 campus | Sydney North | New South Wales

Actual · AirTrunk SYD2 Sydney North Data Center Campus (Project)

Claim 107839 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. AirTrunk Australia portfolio

    AirTrunk · Document date: Aug 1, 2026 · Corroborating

    Source reference: SRC-6071 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/location/australia/

  2. AirTrunk SYD2 expansion announcement

    AirTrunk · Document date: Jun 15, 2023 · Primary

    Source reference: SRC-3282 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://airtrunk.com/ja/70-megawatt-expansion-underway-at-airtrunk-syd2/

Counterparties and capital

AirTrunk · Developer · CMP-0656

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.