AirTrunk SYD2 Sydney North Data Center Campus

Sydney, New South Wales, AustraliaPartially operational
Capacity
120 MW
Planned critical IT
Lead participant
AirTrunk
Developer
Last updated
Aug 27, 2026
Most recent public record update

About AirTrunk SYD2 Sydney North Data Center Campus

AirTrunk's SYD2 campus operates in northern Sydney and has undergone a major expansion. The announced program lifts total capacity above 120 MW. AirTrunk is publicly identified in the project record for Sydney, Sydney North, NSW, AU. The disclosed development record includes more than 120 MW total campus capacity after expansion; 70 MW final-phase expansion; dedicated 200 MVA substation. Power and infrastructure include operational northern Sydney campus supported by a dedicated 132 kV substation. AirTrunk states the SYD2 expansion lifts total campus capacity above 120 MW.

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load120 MWDesign · AirTrunk SYD2 Sydney North Data Center Campus

Development

1 phases · 2 milestones
Operating and expansion programPartially Operational

Project-wide phase for AirTrunk SYD2 Sydney North Data Center Campus; capacity remains classified as it load.

Jun 15, 2023
AirTrunk SYD2 project status and capacity disclosed
Completed
Operational campus with final expansion phases underway
Forecast

Infrastructure

Electric GridPartially Operational

120 MW

AirTrunk states the SYD2 expansion lifts total campus capacity above 120 MW.

Site FacilityPartially Operational

Operational northern Sydney campus supported by a dedicated 132 kV substation.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

8 facts
Location Context
SYD2 campus | Sydney North | New South Wales
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
120 MW
Design
Capacity Basis
AirTrunk states the SYD2 expansion lifts total campus capacity above 120 MW.
Actual
Development Scale
More than 120 MW total campus capacity after expansion
Actual
Development Milestone
70 MW final phase expansion
Actual
Power Arrangement
Dedicated 200 MVA substation.
Actual
Boundary Context
SYD2 campus | Sydney North | New South Wales
Actual