Scope and capacity
AEP's current Baku–Gavin project page records the transmission application filed July 24, 2026 and deemed complete August 28. Application completeness is not construction approval. AEP Ohio transmission program for PORTS: Baku substation, Baku-Gavin 765 kV line and related substations; not generation or campus capacity. AEP Piketon Area Transmission Improvements is located in Piketon, OH, US and is a program in preconstruction status.
Headline: See constituent sites
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (6)
Planned transmission investment · $4.20 billion
Actual · AEP Piketon Area Transmission Improvements (Project)
Claim 33814 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Department announces partnership to ensure affordable energy and power America's AI
U.S. Department of Energy · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1884 · Government record · Recorded authority: Official primary
Source URL
https://www.energy.gov/articles/energy-department-announces-partnership-ensure-affordable-energy-and-power-americas-ai
https://www.energy.gov/articles/energy-department-announces-partnership-ensure-affordable-energy-and-power-americas-ai
- AEP Ohio and SB Energy announce infrastructure plans for PORTS Technology Campus
American Electric Power · Document date: Mar 20, 2026 · Corroborating
Source reference: SRC-1889 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aep.com/news/stories/view/10823/
https://www.aep.com/news/stories/view/10823/
Planned voltage · 765 kV
Actual · AEP Piketon Area Transmission Improvements (Project)
Claim 33815 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Piketon Area Improvements Project
AEP Transmission · Document date: Jul 1, 2026 · Corroborating
Source reference: SRC-1890 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aeptransmission.com/ohio/PiketonArea/
https://www.aeptransmission.com/ohio/PiketonArea/
- Fact sheet: ensuring affordable energy access in Ohio while powering the future
U.S. Department of Energy · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1886 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.energy.gov/articles/fact-sheet-department-energy-ensuring-affordable-energy-access-ohio-while-powering-future
https://www.energy.gov/articles/fact-sheet-department-energy-ensuring-affordable-energy-access-ohio-while-powering-future
- AEP Ohio and SB Energy announce infrastructure plans for PORTS Technology Campus
American Electric Power · Document date: Mar 20, 2026 · Corroborating
Source reference: SRC-1889 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aep.com/news/stories/view/10823/
https://www.aep.com/news/stories/view/10823/
Planned substation count · 4 substations
Actual · AEP Piketon Area Transmission Improvements (Project)
Claim 33816 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Fact sheet: ensuring affordable energy access in Ohio while powering the future
U.S. Department of Energy · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1886 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.energy.gov/articles/fact-sheet-department-energy-ensuring-affordable-energy-access-ohio-while-powering-future
https://www.energy.gov/articles/fact-sheet-department-energy-ensuring-affordable-energy-access-ohio-while-powering-future
Planned baku gavin line length approximately · 50 miles
Actual · AEP Piketon Area Transmission Improvements (Project)
Claim 33817 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Piketon Area Improvements Project
AEP Transmission · Document date: Jul 1, 2026 · Primary
Source reference: SRC-1890 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aeptransmission.com/ohio/PiketonArea/
https://www.aeptransmission.com/ohio/PiketonArea/
Planned power availability year · 2029
Actual · AEP Piketon Area Transmission Improvements (Project)
Claim 33818 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- AEP Ohio and SB Energy announce infrastructure plans for PORTS Technology Campus
American Electric Power · Document date: Mar 20, 2026 · Primary
Source reference: SRC-1889 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aep.com/news/stories/view/10823/
https://www.aep.com/news/stories/view/10823/
Opsb case reference · 26-0426-EL-BTX
Actual · AEP Piketon Area Transmission Improvements (Project)
Claim 33819 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Piketon Area Improvements Project
AEP Transmission · Document date: Jul 1, 2026 · Primary
Source reference: SRC-1890 · Company announcement · Recorded authority: Party primary
Source URL
https://www.aeptransmission.com/ohio/PiketonArea/
https://www.aeptransmission.com/ohio/PiketonArea/
Counterparties and capital
$4,200,000,000 · Mar 20, 2026
SB Energy commitment for AEP transmission supporting PORTS; approvals pending.
AEP Ohio (Transmission developer) · SB Energy (Funding counterparty)
Sources (2)
Financing record 99; claim-specific source links appear in the exhibit sources where published.