Cartis site intelligence
AI data center sites
Search property-level records across markets, participants, capacity, development activity, infrastructure and supporting evidence.
970 site records69 program records1022 fully connected17 sourced research records
Site and program directory
Search markets, owners, developers, operators, utilities and connected organizations.
6 results · 50 per page
RecordStatusCapacityOwner / developerLast verified
Prometheus WY-2Reviewed site record
Casper, Wyoming, United States
Prometheus Hyperscale
Proposed
1,500 MW
Planned / designPrometheus Hyperscale
Aug 28, 2026
Prometheus Hyperscale Evanston Data Center CampusReviewed site record
Evanston, Wyoming, United States
Prometheus Hyperscale
Entitled / Permitted
1,250 MW
Planned / designPrometheus Hyperscale
Aug 27, 2026
Related Digital Cheyenne CampusReviewed site record
Cheyenne, Wyoming, United States
Black Hills EnergyCity of Cheyenne
Under construction
420 MW
Planned / designRelated Digital
Aug 25, 2026
Crusoe Tallgrass WyomingReviewed site record
Cheyenne, Wyoming, United States
CrusoeGoogle
On hold / Delayed
—
Not disclosedCrusoe
Aug 28, 2026
Microsoft Cheyenne Expansion ProgramReviewed program record
Cheyenne, Wyoming, United States
Black Hills EnergyCity of Cheyenne
Status Under Review
—
Not disclosedMicrosoft
Aug 24, 2026
Microsoft Highlands Data Center DevelopmentReviewed site record
Southeast Cheyenne / Highlands, Wyoming, United States
Microsoft
Preconstruction
—
Not disclosedMicrosoft
Aug 24, 2026
Every figure carries its capacity stage. Operating, contracted, planned/design and utility-service values remain distinct; generation is never used as site capacity, and unsupported values remain undisclosed.