Data center siteSite record

Related Digital Cheyenne Campus

Cheyenne, Wyoming, United StatesUnder construction
Capacity
420 MW
Planned / design
Lead participant
Related Digital
Operator
Last updated
Aug 25, 2026
Most recent public record update

About Related Digital Cheyenne Campus

Related Digital is building a data center campus in Cheyenne whose first 184,000-square-foot building is leased to CoreWeave for 88 MW of critical IT capacity. The current up-to-420 MW campus figure is a future design envelope, not operating load.

Projects sharing a market, utility, or organization.

2 related

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design420 MWDesign · Related Digital Cheyenne Campus
Design88 MWDesign · Related Digital Cheyenne Campus

Development

2 phases · 3 milestones
First building / CoreWeave phaseUnder Construction

184,000 sf on 36 acres with 88 MW critical IT; late-2026 completion remains a target.

1 building

Future campus expansionAnnounced Or Preconstruction

Current future envelope supersedes the 302 MW launch scope for marketing, but neither is delivered capacity.

Oct 7, 2025
First 88 MW CoreWeave building breaks ground
Completed
Apr 4, 2026
Local reporting confirms construction underway
Completed
Oct 1, 2026
First building completion target
Forecast

Infrastructure

Electric GridPlanned Or Represented

Black Hills Energy service is identified; contracted and energized MW are undisclosed.

Cooling SystemUnder Construction

Air-cooled chillers support a nominal-water-use design claim.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1Cooling & water: 1

Facts & sources

Published claims and their source links.

15 facts
Current Full Campus Design Capacity
420 MW
Design
First Building Critical It Capacity
88 MW critical IT
Design
Campus Area
115 acres
Fact
First Phase Site Area
36 acres
Fact
First Building Floor Area
184,000 square feet
Fact
Status
Construction
Actual
Construction Start
2025-10-07
Actual
Target Completion
Late 2026
Fact
Anchor Tenant
CoreWeave
Actual
Lease Term Characterization
Long term
Actual
First Phase Investment Estimate
$1.20 billion
Fact
Cooling Design
Air cooled chillers
Actual
Electric Service Provider
Black Hills Energy
Actual
Construction Manager
Clayco
Actual
Capacity Boundary Decision
88 MW leased phase; 302 MW launch history; up to 420 MW current future design
Actual