Yondr Loudoun County Data Center Campus

Leesburg, Virginia, United StatesPartially operational
Capacity
336 MW
Planned critical IT
Lead participant
Yondr Group
Developer
Last updated
Aug 28, 2026
Most recent public record update

About Yondr Loudoun County Data Center Campus

Yondr’s Northern Virginia record combines a completed 48 MW building, phased delivery of a second 48 MW building and a separate 240 MW adjacent pipeline. The 336 MW figure is therefore a campus-plus-pipeline ceiling, not live load. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Projects sharing a market, utility, or organization.

1 related

Capacity

Planned critical IT
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
It Load336 MWDesign · Yondr Loudoun County Data Center Campus
Future Potential336 MWDesign · Yondr Loudoun County Data Center Campus

Development

1 phases · 2 milestones
Operating facility and documented expansionOperational

Yondr’s Northern Virginia record combines a completed 48 MW building, phased delivery of a second 48 MW building and a separate 240 MW adjacent pipeline. The 336 MW figure is therefore a campus-plus-pipeline ceiling, not live load. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Dec 17, 2025
First 12 MW of the second building reached ready-for-service
Completed
Aug 29, 2026
Project-specific source review refreshed
Completed

Infrastructure

Electric GridOperational

336 MW

Facility IT boundary; customer utilization is not disclosed.

FiberOperational

Carrier-neutral or resilient fibre connectivity described for the individual facility.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Fiber & connectivity: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Yondr Northern Virginia Campus | Leesburg | VA | US
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
336 MW
Design
Capacity Basis
Yondr publishes 336 MW of total critical cloud capacity for the Loudoun County campus.
Actual
Location Context
Yondr Northern Virginia Campus | Leesburg | VA | US
Actual
Lifecycle Status
Partially operational
Actual
Reported Capacity
336 MW
Design
Capacity Basis
336 MW combines a 96 MW campus—partly operating—with a separate 240 MW adjacent pipeline; it is not current operating load.
Actual
Operator Confirmed
Yondr Group
Actual
Facility Capacity Basis
336 MW combines a 96 MW campus—partly operating—with a separate 240 MW adjacent pipeline; it is not current operating load.
Actual
Current Lifecycle
Partly operating with further delivery underway
Actual
Evidence Boundary
Facility specific evidence; campus or portfolio figures are not transferred between records
Actual