Cartis diligence evidence schedule

Yondr London Campus Building 3

PRJ-1024 · Site · Slough, England, United Kingdom

Record last updated Oct 28, 2026

Scope and capacity

Yondr London Campus Building 3 is a separately tracked building within Yondr’s Wexham Road campus. The three-building program totals just over 100 MW: 30 MW Building 1, 30 MW Building 2 and 40 MW Building 3. Shared-campus permits and infrastructure do not turn the combined total into this building’s capacity. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.

Headline: 40 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Yondr Slough Building 3 | Slough | England | GB

Actual · Yondr London Campus Building 3 (Project)

Claim 68043 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Lifecycle status · Construction

Actual · Yondr London Campus Building 3 (Project)

Claim 68044 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Reported capacity · 40 MW

Design · Yondr London Campus Building 3 (Project)

Claim 68045 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Capacity basis · Yondr publishes 40 MW for the third London campus building.

Actual · Yondr London Campus Building 3 (Project)

Claim 68046 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Location context · Yondr Slough Building 3 | Slough | England | GB

Actual · Yondr London Campus Building 3 (Project)

Claim 80930 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Lifecycle status · Construction

Actual · Yondr London Campus Building 3 (Project)

Claim 80931 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Reported capacity · 40 MW

Planned / design or future potential · Yondr London Campus Building 3 (Project)

Claim 80932 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Capacity basis · 40 MW is a published future facility or full build IT boundary; it is not operating load.

Actual · Yondr London Campus Building 3 (Project)

Claim 80933 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Operator confirmed · Yondr Group

Actual · Yondr London Campus Building 3 (Project)

Claim 80934 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Facility capacity basis · 40 MW is a published future facility or full build IT boundary; it is not operating load.

Actual · Yondr London Campus Building 3 (Project)

Claim 80935 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Current lifecycle · Under development

Actual · Yondr London Campus Building 3 (Project)

Claim 80936 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Yondr London Campus Building 3 official profile

    Yondr Group · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-3875 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://www.yondrgroup.com/newsroom/press-release/yondr-group-breaks-ground-on-third-phase-of-100mw-london-campus/

Counterparties and capital

Yondr Group · Developer · CMP-1426

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.