Scope and capacity
Yondr’s Ragow project has a published 42 MW full-build design, but recent local reporting says construction has not progressed despite a building permit reported in 2024. The record remains development-stage and the headline is a design boundary only. Phase-by-phase energization, tenant utilization, contract pricing and any undisclosed financing remain outside the verified public record.
Headline: 42 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (13)
Location context · Yondr Berlin Campus | Ragow | Brandenburg | DE
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 68035 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Lifecycle status · Construction
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 68036 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Reported capacity · 42 MW
Design · Yondr Berlin Ragow Data Center Campus (Project)
Claim 68037 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Capacity basis · Yondr publishes 42 MW for the full Berlin project.
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 68038 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Location context · Yondr Berlin Campus | Ragow | Brandenburg | DE
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80912 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Lifecycle status · Construction
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80913 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Reported capacity · 42 MW
Planned / design or future potential · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80914 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Capacity basis · 42 MW is a published future facility or full build IT boundary; it is not operating load.
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80915 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Operator confirmed · Yondr Group
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80916 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Facility capacity basis · 42 MW is a published future facility or full build IT boundary; it is not operating load.
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80917 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Current lifecycle · Under development
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80918 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Yondr Berlin Ragow Data Center Campus official profile
Yondr Group · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3872 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
https://www.yondrgroup.com/newsroom/press-release/berlin-provides-major-connectivity-hub-for-yondrs-latest-data-center-project/
Permit status · Building permit reported issued in 2024
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80920 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Ragow data-center permit and construction status
Märkische Allgemeine · Document date: Aug 21, 2026 · Primary
Source reference: SRC-4581 · News report · Recorded authority: Secondary
Source URL
https://www.maz-online.de/lokales/dahme-spreewald/mittenwalde/rechenzentrum-in-ragow-baugenehmigung-seit-2024-doch-baustelle-steht-still-FDH6VWPY6NDSPL33P5STIZZDZI.html?outputType=valid_amp
https://www.maz-online.de/lokales/dahme-spreewald/mittenwalde/rechenzentrum-in-ragow-baugenehmigung-seit-2024-doch-baustelle-steht-still-FDH6VWPY6NDSPL33P5STIZZDZI.html?outputType=valid_amp
Construction status · Recent reporting says the site remained stalled
Actual · Yondr Berlin Ragow Data Center Campus (Project)
Claim 80921 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Ragow data-center permit and construction status
Märkische Allgemeine · Document date: Aug 21, 2026 · Primary
Source reference: SRC-4581 · News report · Recorded authority: Secondary
Source URL
https://www.maz-online.de/lokales/dahme-spreewald/mittenwalde/rechenzentrum-in-ragow-baugenehmigung-seit-2024-doch-baustelle-steht-still-FDH6VWPY6NDSPL33P5STIZZDZI.html?outputType=valid_amp
https://www.maz-online.de/lokales/dahme-spreewald/mittenwalde/rechenzentrum-in-ragow-baugenehmigung-seit-2024-doch-baustelle-steht-still-FDH6VWPY6NDSPL33P5STIZZDZI.html?outputType=valid_amp
Counterparties and capital
Yondr Group · Developer · CMP-1426
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.