Cartis diligence evidence schedule
Yahoo Quincy Data Center Campus
PRJ-1188 · Site · Quincy, Washington, United States
Record last updated Oct 28, 2026
Scope and capacity
Yahoo operates a data-center campus in Quincy, Washington, within Grant County PUD’s hydroelectric service territory. The site is part of a regional concentration of large data centers connected to low-cost Columbia River power. A current campus IT-capacity figure has not been disclosed.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (1)
Utility service territory · Grant County PUD
Actual · Yahoo Quincy Data Center Campus (Project)
Claim 155043 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 28, 2026
- ENERGY STAR certified data centers
U.S. Environmental Protection Agency · Document date: Aug 31, 2026 · Corroborating
Source reference: SRC-7466 · Government record · Recorded authority: Official primary
Source URL
https://www.energystar.gov/buildings/certified-data-centers
https://www.energystar.gov/buildings/certified-data-centers
- Data centers and Grant PUD
Grant County PUD · Document date: Aug 28, 2026 · Primary
Source reference: SRC-7465 · Company announcement · Recorded authority: Party primary
Source URL
https://www.grantpud.org/blog/data-center-faqs
https://www.grantpud.org/blog/data-center-faqs
Counterparties and capital
Grant County PUD · Utility provider · CMP-1658
Yahoo Inc. · Operator · CMP-1674
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.