Wonder Valley AI Data Centre Park

Grande Prairie region, Alberta, CanadaPreconstruction
Evidence
Planned / design
7,500 MW
Updated
Oct 28, 2026

The project’s Spring 2026 newsletter, hosted by the municipality, targets construction in 2027 subject to approvals, initial power in 2028 and phased buildout from 2029 over more than ten years. These remain development forecasts; power availability is not a data center opening. Wonder Valley is a planned AI data center park in Alberta’s Municipal District of Greenview. O’Leary Ventures’ master plan spans roughly 8,000 acres and more than 50 facilities, with a first phase listed by Alberta at approximately C$12 billion. The 7.5 GW figure is the proposed full-development power envelope, not operating IT load.

Capacity

Reported capacity

Planned / design or future potential

7,500 MW

Source

Capacity

Planned / design or future potential

7,500 MW

Source

Capacity basis

Planned / design or future potential

7,500 MW proposed full development site power envelope

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development programAnnounced or preconstruction

Wonder Valley AI Data Centre Park: Development program.

Milestones (2)
Wonder Valley AI Data Centre Park — Development program

Date not disclosed · Event timing type not established

In progress · Announced

Source not linked
Wonder Valley is a planned AI data center park in Alberta’s Municipal District of Greenview.

Date not disclosed · Event timing type not established

In progress · Status changed

Source not linked

Participants

O’Leary Ventures

Developer

Sources by role
Developer (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Development scale

Actual

Wonder Valley is a planned AI data center park in Alberta’s Municipal District of Greenview. O’Leary Ventures’ master plan spans roughly 8,000 acres and more than 50 facilities, with a first phase listed by Alberta at approximately C$12 billion

Source

Financing records

Investment commitment

CA$12,000,000,000

Jan 1, 2026

First-phase project investment listed by Alberta.

Parties & sources

O’Leary Ventures (Sponsor)

Site & development

Location context

Actual

Grande Prairie region, Alberta, Canada

Source

Location

Actual

Grande Prairie region, Municipal District of Greenview No. 16, AB, CA

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

Planned full build campus envelope

Source

Project identity

Actual

Wonder Valley AI Data Centre Park

Source

Lifecycle status

Actual

Development program

Source

Participant roles

Actual

O’Leary Ventures

Source

Infrastructure

Actual

The 7.5 GW figure is the proposed full development power envelope, not operating IT load.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

7,500 MW

7,500 MW proposed full-development site power envelope

Site facility

Planned or represented

The 7.5 GW figure is the proposed full-development power envelope, not operating IT load.