Cartis diligence evidence schedule
WhiteFiber Austin County AI Data Center Campus
PRJ-0709 · Site · Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
Available public filings do not substantiate WhiteFiber or Bit Digital as the developer of an Austin County, Texas campus. The 285 MW Austin County project previously associated with this page is disclosed by CleanSpark, so it is not attributed here. WhiteFiber, Bit Digital is associated with the development in Austin County, TX, US. The disclosed development scope includes the cited 285 MW Austin County filing belongs to CleanSpark; no project-specific WhiteFiber development document has been identified for this named campus. Power and physical infrastructure include no corroborated project-specific power, building or interconnection arrangement is stated for this named WhiteFiber campus. The 285 MW figure belongs to a separate CleanSpark project and is not a defensible capacity figure for this identity. The available public sources do not establish a project-scoped operating or contracted capacity figure.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (9)
Location context · WhiteFiber campus | Austin County | Texas
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 57976 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Lifecycle status · Preconstruction
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 57977 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Capacity basis · The company reports 285 MW under long term power supply agreements.
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 57979 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Location context · WhiteFiber campus | Austin County | Texas
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 111443 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Lifecycle status · Preconstruction
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 111444 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Development scale · The cited 285 MW Austin County filing belongs to CleanSpark
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 111463 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- WhiteFiber investor filings and current footprint
WhiteFiber · Document date: Aug 1, 2026 · Corroborating
Source reference: SRC-6254 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.whitefiber.com/investors
https://www.whitefiber.com/investors
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Development milestone · No project specific WhiteFiber development document has been identified for this named campus.
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 111464 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- WhiteFiber investor filings and current footprint
WhiteFiber · Document date: Aug 1, 2026 · Corroborating
Source reference: SRC-6254 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.whitefiber.com/investors
https://www.whitefiber.com/investors
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Power arrangement · The project identity and its relationship to the documented CleanSpark Austin County development remain unresolved.
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 111465 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- WhiteFiber investor filings and current footprint
WhiteFiber · Document date: Aug 1, 2026 · Corroborating
Source reference: SRC-6254 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.whitefiber.com/investors
https://www.whitefiber.com/investors
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Site configuration · WhiteFiber campus | Austin County | Texas
Actual · WhiteFiber Austin County AI Data Center Campus (Project)
Claim 111466 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- WhiteFiber investor filings and current footprint
WhiteFiber · Document date: Aug 1, 2026 · Corroborating
Source reference: SRC-6254 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.whitefiber.com/investors
https://www.whitefiber.com/investors
- Bit Digital 2025 annual report
Bit Digital · Document date: Jan 30, 2026 · Primary
Source reference: SRC-3173 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
https://www.sec.gov/Archives/edgar/data/0000827876/000119312526019478/2026_ars.pdf
Counterparties and capital
Bit Digital · Owner · CMP-1450
WhiteFiber · Developer · CMP-1449
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.